Repair and maintenance aps. Project for the production of works for the installation and commissioning of an automatic fire alarm and warning system

Ministry of Instrumentation, Automation and Control Systems

(Minpribor)

DEPARTMENTAL BUILDING REGULATIONS

REGULATIONS
DEVELOPMENT OF PROJECTS OF PRODUCTION OF WORKS
FOR INSTALLATION OF AUTOMATIC FIRE EXTINGUISHING INSTALLATIONS
AND INSTALLATIONS OF SECURITY, FIRE AND SECURITY-FIRE ALARMS

VSN 25-09.66-85

Contributed by the All-Union Industrial Association "Soyuzspetsavtomatika"

Instead of VMSN 58-77

These rules have been developed in addition to SN 47-74 and establish requirements for the composition, content, procedure for the development and approval of work projects (PPR) for the installation of automatic fire extinguishing installations (AUP) and security, fire and fire alarm systems (OS, PS , OPS) performed by organizations of the VPO Soyuzspetsavtomatika.

PPR are developed in order to determine the most effective methods fulfillment installation work, ensuring safety and high labor productivity, helping to reduce their cost and labor intensity, reduce the time of installation work and improve their quality. It is not allowed to carry out installation work without projects for the production of work.

1. GENERAL PROVISIONS

1.1. When developing a PPR, the following requirements should be met:

a) state and industry standards;

b) chapters of building codes and regulations and other normative documents on production and acceptance, as well as the economics of construction and installation works approved by the USSR State Construction Committee;

c) departmental regulatory documents for installation work approved by the Ministry of Instrumentation, VPO Soyuzspetsavtomatika and these rules;

d) orders and orders of the Ministry of Instrumentation, VPO Soyuzspetsavtomatika.

1.2. PPR should be developed taking into account:

a) characteristic features specific object and local installation conditions;

b) application of the most advanced forms of planning, organization and management of installation work;

c) application of technological processes that ensure the required level of quality of work;

d) increasing the level of industrialization of installation work;

e) reducing labor intensity and reducing labor costs due to the transfer of a significant part of the volume from the installation site to the installation and preparation sites (MZU);

f) widespread use of unified and typed assembly units, structures and products;

g) complete deliveries of technical means of AUP, OS, PS, OPS and the container method of supplying products and materials.

1.3. It is necessary to start developing a PPR if:

a) approved design and estimate documentation or inspection report;

b) contracts for the production of installation work.

1.4. When developing a PPR for the installation of AUP, OS, PS, OPS, it is necessary to be guided by:

a) standard operating PPR (if any in the installation organization);

b) technological documentation for the production of installation work.

1.5. PPR for the installation of AUP and OS, PS, OPS installations, as a rule, should be developed by the installation organization. It is allowed to develop a WEP for the installation of AFS and installations of OS, PS, OPS for large and unique objects by the design organization, provided that the customer submits a limit for design and survey work, in this case, the installation organization must transfer the necessary initial data to the WEP developer (according to these rules) and provide coordination and approval of WEP.

1.6. Supervision over the performance of technically complex installation work, in cases stipulated by the terms of reference for the development of the PPR, should be carried out by the organization that developed the PPR.

1.7. The text part of the PPR must be carried out in accordance with the requirements of GOST 2.105-79, and the graphic part - in accordance with the requirement of GOST 2.104-68, the format of the sheets must comply with the requirements of GOST 2.301-68.

1.8. In the case of developing a PPR using a computer, it is necessary to be guided by the technical documentation of the automated control system for assembly and commissioning production (ACS MNP) and these rules.

The type and completeness of the technical documentation of the ACS MNP must comply with the requirements of GOST 24.101-80.

2. INITIAL DATA FOR THE DEVELOPMENT OF WEP

4.2. General information for the facility must be drawn up in the form in accordance with the mandatory installation of OS, PS, OPS installations and in the form - AUP installations.

4.3. The explanatory note to the PPR, as a rule, includes the following information:

a) a brief description of object (number of storeys, type of building, height of premises, type of heating, electricity supply, presence of a basement);

b) description of the technology for the production of certain types of work;

c) a technological route map for rigging work, developed taking into account the requirements of the "Rules for the Design and Safe Operation of Load-Lifting Cranes", as well as information letters from the USSR Gosgortekhnadzor bodies;

d) instructions on the organization of warehouse and tool management (the procedure for providing warehouse space and special conditions for storing tools and means of labor);

e) instructions for testing and commissioning the installation (according to the "Rules for the production and acceptance of work. Automatic fire extinguishing installations" and "Rules for the production and acceptance of work. Installations of security, fire and fire alarm systems");

f) instructions for monitoring and assessing the quality of installation work;

g) calculation of the coefficient of industrialization, determined in accordance with " Guidelines on the calculation of technical and economic indicators of the mechanization of installation work, approved by the VPO Soyuzspetsavtomatika on November 17, 1977.

4.4. It is allowed not to provide information on those documents of the explanatory note, work on which is not provided for by the project or the survey report.

4.5. The list of physical volumes of work and labor costs, as recommended, is compiled on the basis of design estimates, price tags, uniform norms and rates, departmental norms and rates, and local norms.

4.6. The picking list for instruments and equipment supplied by the general contractor (customer) must be drawn up in the form in accordance with the mandatory.

4.7. The picking list for installation materials must be drawn up in accordance with the mandatory form and, upon delivery of materials by the customer or general contractor, be agreed with representatives of the relevant organizations.

4.8. The picking list of mounting products supplied by the Soyuzspetsavtomatika factories must be drawn up in the form recommended.

4.9. Drawings and sketches are attached to the picking list for products, enlarged units and blocks assembled at the MZU, according to the recommended one.

4.10. The list of building structures for the installation of instruments and equipment should be drawn up in the form recommended, indicating the deadlines by which building organizations must hand over these structures for installation. The list must be agreed with the customer and the general contractor.

4.11. The technological route map of rigging operations is a diagram of the route for moving large assemblies, blocks and other equipment weighing more than 60 kg from the MZU or warehouse to the installation site, while the route on the territory of the facility must be plotted on a copy from the general plan, where the following must be indicated:

a) places of installation of truck cranes or other lifting mechanisms;

b) the minimum allowable distances from the extreme overall points of mobile lifting mechanisms to buildings and structures, as well as to stored materials, structures, etc.;

c) the distance from the lifting mechanism to power lines, places of traffic, pedestrians;

d) areas for storage of goods;

e) fencing of hazardous areas;

f) methods of slinging individual most complex units to be lifted or moved, etc.

If necessary, it is allowed to apply other data required for carrying out rigging work on the copy.

The map should indicate the mechanisms and devices necessary to perform rigging and transport work, as well as the sequence of transportation and movement of goods.

4.12. The list of necessary tools, fixtures and mechanisms (not included in the approved set for the brigade) should be drawn up in the form recommended.

4.13. A list of the breakdown of the facility into installation zones and the need for materials and equipment by zones should be drawn up in the form recommended.

4.14. The special labor safety requirements, drawn up in the form in accordance with the mandatory, should reflect specific safety measures for the implementation of installation work at this facility (work at height, with electrified tools, gas welding, in electrical installations, for moving mounting elements in the installation area, loading and unloading, etc.).

4.15. The calendar schedule for the production of installation work according to the mandatory must be drawn up in accordance with the stages of work, broken down into separate types of work or technological operations. The scope of work is taken from the estimates for the project. The composition of the link, the labor intensity per unit of work is taken taking into account the achieved output.

4.16. The map of operational quality control of installation work should be compiled in accordance with the recommended.

5. COORDINATION AND APPROVAL OF WEP

5.1 The installation organization, together with the developer, coordinates the WEP with the general contractor (customer) in the form of a letter (minutes), or signatures on the title page, on tracing papers or copies of the relevant documents.

5.2. The following documents from the composition of the PPR are subject to agreement with the general contractor (customer):

a) the calendar schedule for the production of installation work;

b) picking lists for instruments, equipment, materials;

c) a list of building structures;

d) a list of the breakdown of the facility into installation zones and the need for equipment and materials by zones.

5.3. The prepared WEP is approved by the chief engineer of the installation department (if necessary, it is preliminarily reviewed at the technical Management Council) and the project is stamped “To production”.

5.4. The binding of standard WEPs and WEPs of repeated application to specific conditions must be agreed and approved in the same manner as newly developed WEPs.

5.5. The terms for the development and transfer of WEP are established in the terms of reference for its development.

Appendix 1

AGREED

____________

(position)

___________________________

___________________________

(name of company

customer)

___________________________

___________________________

(the date)

APPROVE

Chief Engineer

___________________________

___________________________

(name of assembly

organizations)

___________________________

(signature, surname, initials)

___________________________

(the date)

TECHNICAL TASK
(the form)

for the development of WEP for installation _______________________

(name of AUP

or installation of OS, PS, OPS)

1. __

(Object name)

2. Customer of PPR _________________________________________________________________

(name and

________________________________________________________________________________

organization address)

3. Developer of WEP ______________________________________________________________

(name and

________________________________________________________________________________

organization address)

4. Work production time:

Beginning ____________________ 19 _____

End ____________________ 19 _____

5. Customer of the object _______________________________________________________________

(name and

________________________________________________________________________________

organization address)

6. General contractor ______________________________________________________________

(name and

________________________________________________________________________________

organization address)

7. Data on the breakdown of the facility into installation stages in accordance with the contract

________________________________________________________________________________

________________________________________________________________________________

________________________________________________________________________________

8. Data on installation tools, mechanisms, lifting equipment and transport available to the installation organization

Name (brand) of the tool, mechanism, equipment, transport

Execution, modification, characteristic

Quantity, pcs.

Note

1.
2.
3.
etc.

9. Other requirements, including special installation conditions, the need for architectural supervision ________________________________________________________________________________

________________________________________________________________________________

________________________________________________________________________________

10. List of original technical documentation attached to the terms of reference

Title of the document

Document designation

Document Developer

etc.

Annex 2

Mandatory

Ministry of Instrumentation, Automation and Control Systems

VPO "Soyuzspetsavtomatika"

Production Association ____________________________________________________

CMNU _______________________________________________________________________________

APPROVE

Chief Engineer

__________________________

(name of SMNU)

__________________________

(signature, first and last name)

"____" ____________ 19 ___

PROJECT OF WORK PRODUCTION (the form)

(Name

________________________________________________________________________________

settings)

________________________________________________________________________________

(Object name)

Annex 3

Mandatory

________________________________________________________________________________

(name of ministry)

________________________________________________________________________________

(name of organization - developer of WEP)

APPROVE

Chief Engineer

______________________

(name of SMNU)

ON __________________

(Name)

________ (I.O. Surname)

(signature)

"____" _________ 19___

PROJECT OF WORK PRODUCTION (the form)

for the installation of systems ________________________________________________________________

(Name

________________________________________________________________________________

settings)

________________________________________________________________________________

(Object name)

AGREED

___________________________

(position)

___________________________

(name of company -

general contractor (customer)

_____________ (I.O. Surname)

(signature)

"_____" _____________ 19___

_____________________________

(supervisor)

_____________________________

(name of company -

developer of PPR)

_______________ (I.O. Surname)

(signature)

"____" _____________19___

Labor protection engineer

_______________ (I.O. Surname)

(signature)

"_____" ______________ 19____

Appendix 4

Mandatory

GENERAL INFORMATION ON THE OBJECT (the form)

1. Name of the object, code ________________________________________________________

2. Project organization: _________________________________________________________

3. Customer: _____________________________________________________________________

4. General contractor:_________________________________________________________________

5. Agreement No. ___________ dated "_____" ______ 19____.

6. Total estimated cost ____________________________ rub.

7. The cost of installation work __________________________ rub.

8. Cost adjustment works _________________________ rub.

9. Deadline for entering the object _____________________________________________________________

10. Duration of work ___________________________________________

11. The complexity of installation work ______________________ people / hour.

12. The complexity of adjustment work ______________________ people / hour.

13. Average output _________________________________ rub.

14. Number of workers by profession:

a) ____________________________ people d) _____________________________ people

b) ____________________________ people e) _____________________________ people

c) ____________________________ people f) _____________________________ people

Appendix 5

Mandatory

GENERAL INFORMATION ON THE OBJECT (the form)

1. Name of the object, code _________________________________________________

2. Design organization ____________________________________________________________

3. Customer ____________________________ account No. ______________________________

4. General contractor _______________________ account No. ______________________________

5. Agreement No. _________________ dated "_____" ________________ 19 ___

6. Total estimated cost ______________________________ rub.

7. The cost of installation work ____________________________ rub.

Including cost:

a) the technological part ________________________________ rub.

b) electrical part ___________________________________ rub.

8. The cost of adjustment work ____________________________ rub.

9. Protected area __________________________________ m 2

10. Number of sections ___________________________________ pcs.

11. Deadline for commissioning the object ______________________________________________________________

12. Duration of work _____________________________________________

13. Labor intensity of installation work ________________________ people / hour.

including labor intensity:

a) technological part _________________________________ person/hour.

b) electrical part _________________________________ person/hour.

14. Labor intensity of adjustment works ________________________ man/hour.

15. Average output ____________________________________ rub.

16. Number of workers by profession:

a) ____________________ people d) ____________________ people

b) ____________________ people e) ____________________ people

c) ____________________ people f) ____________________ pers.

17. Data and terms of the construction and technological readiness of the object for the production of installation works (according to the acts of checking the readiness of the object No. ___________ dated "______" __________________________________________):

a) the readiness of the premises subject to fire protection _______________________

b) the readiness of the premises for the pumping station ___________________________________________

c) the presence of water inlets ________________________________________________

d) the presence of an on-site workshop, warehouse ____________________________________________

e) availability of household and utility rooms _______________________________________

f) provision of materials and equipment ____________________________________

g) availability of power supply ______________________________________________

h) the presence of embedded parts __________________________________________________________

18. Decisions on postponing the start of installation work and the commissioning date in accordance with act No. _______

from "_____" ______ 19_____

(in cases of violation of the terms of construction readiness and its completion with equipment and materials)

____________________________________________________________________________

____________________________________________________________________________

Appendix 6

STATEMENT
physical volume of work and labor costs
(the form)

Name of works

units rev.

Quantity by

Per unit

For all work

project

according to the PPR

project

PPR

norm of time, person/hour

rate

item of installation work (rub.)

norm of time, person/hour

salary (rub.)

item of installation work (rub.)

norm of time, person/hour

salary (rub.)

etc.

Total:

Compiled by: __________________ _________________ _____________________

(position)

"_____" _______________19 _____

Appendix 7

Mandatory

PACKING LIST

for instruments and equipment of the general contractor (customer) (the form)

Name

Type, brand

unit of measurement

Quantity

Delivery time to the object

Note

etc.

Appendix 8

Mandatory

PACKING LIST

mounting materials (the form)

The supplier_____________________________________________________________________

(name of company)

Name of materials (brand, size, GOST)

unit of measurement

Total

including:

Note

directly to the installation area

for processing (at MZU)

amount

delivery time

amount

delivery time

etc.

Annex 9

PACKING LIST
assembly products supplied by Soyuzspetsavtomatika factories
(the form)

Name of mounting products

Normal or drawing number

Product marking

unit of measurement

Quantity

Delivery time to the object

Note

1.
2.
3.
etc.

Compiled by: ___________________________________

(position)

____________________________________________

(signature) (surname, initials)

"_____" ______________ 19 _____

Annex 10

PACKING LIST
for products, enlarged units and blocks assembled at the MZU
(the form)

Node or block name

Normal or drawing number

Quantity

character number

Delivery time to the object

Note

etc.

Compiled by: ________________________________________

(position)

_________________________________________________

(signature) (surname, initials)

"_____" _______________ 19 _____

Annex 11

SCROLL
building structures
(the form)

Name of structures

No. of working drawings

Completion date

Note

etc.

Annex 12

SCROLL
necessary tools, fixtures and mechanisms

(the form)

Name of tools, devices and mechanisms

Type, brand

unit of measurement

Quantity

Note

etc.

Appendix 13

STATEMENT
division of the object into mounting zones
and needs of equipment and materials by zones
(the form)

Installation zone name

Name of equipment and materials by installation areas

Unit of measurement

Quantity

Delivery time

Note

etc.

Annex 14

Mandatory

SPECIAL SAFETY REQUIREMENTS

(the form)

Technological operation

Place of work with increased danger

Additional labor safety measures

etc.

Appendix 15

Mandatory

CALENDAR SCHEDULE FOR ASSEMBLY WORKS ON THE FACILITY

(the form)

Name of works

Scope of work

The composition of the link

Labor intensity, person/hour

Time to complete the work (in days from the day the work began)

units rev.

amount

etc.

etc.

Annex 16

OPERATIONAL QUALITY CONTROL CHART

(the form)

Main processes and operations to be controlled

Composition of control (what is checked)

Technical equipment of control (what is checked)

Type of control (mode and frequency)

Direct control (who controls)

Places of registration of control results (as-built documentation)

Send your good work in the knowledge base is simple. Use the form below

Students, graduate students, young scientists who use the knowledge base in their studies and work will be very grateful to you.

There is no HTML version of the work yet.
You can download the archive of the work by clicking on the link below.

Similar Documents

    Determination of the nomenclature and scope of work. The choice of methods for the production of construction and installation works, the main machines and mechanisms. Calculation of the volume of earthworks. Installation of structures, execution of joints and knots. Technical and economic indicators of the construction plan.

    thesis, added 01/24/2016

    Scheduling, taking into account the complexity of the types of work and the standard duration of the construction of the facility. Architectural and planning characteristics of the building. Formation of technological complexes of work and breakdown of the general front of work into private ones.

    term paper, added 06/02/2009

    Substantiation of installation methods for a prefabricated building. Determination of labor intensity of work. Load-handling devices and devices for mounting and temporary fastening of the structure. Organization and technology of the construction process. Work schedule.

    term paper, added 12/23/2015

    Organizational and technological scheme of the construction of the facility. Work production methods. Table of works and resources of the network diagram. Estimated cost. Technical and economic indicators for the project of a panel-block 3-section 11-storey residential building.

    term paper, added 06/21/2009

    Development of the installation of a one-story industrial building. Determination of the labor intensity of the work carried out, the composition of the assembly links. Selection of transport and inventory. Routing for the installation of columns of the middle row, the work schedule.

    term paper, added 01/08/2013

    Determining the scope of earthworks at the construction site. Selection and justification of production methods, calculation of the volume of the pit, machine capacity and duration; distribution of earth masses, excavator slaughter scheme. Calendar chart; occupational Safety and Health.

    term paper, added 08/27/2012

    Characteristics of ventilation equipment and construction and installation works. Calendar planning. Calculation of the labor intensity of the work performed, the need for materials and structures, the number of personnel. Technical and economic indicators of the construction plan.

    term paper, added 06/27/2016

    Natural and climatic characteristics of the construction area. The choice of structures and the method of their installation. Technology of installation of structures with the selection of devices. Determining the scope of work. Calculation of labor costs. Calendar plan production of works.

    term paper, added 06/17/2014

CJSC "AUTOMATIC"

Object: Branch of JSC "OMK-Steel". Foundry and rolling complex.

Shredded scrap production area. Shelter of non-ferrous sorting area

PROJECT OF WORK PRODUCTION

P.106.2015-PPR

Project for the production of works for the installation and commissioning of an automatic fire alarm and warning and evacuation control systems

Vyksa, Nizhny Novgorod Region

LIST OF SHEETS OF THE MAIN SET

Name

Note

1 General data

1.1 List of sheets of the main set

1.2 List of referenced and attached documents

1.4 List of main sets of working drawings

1.5 General information

2. Characteristics of the object and construction conditions

3. Choice rational ways work

4. Separation of the scope of work at the facility by type, performer and site

5. Determining the duration of installation and labor intensity of work

6. Calculation of the need for labor and material and technical resources

7. Feasibility studies project indicators

8. Organization of production and installation and commissioning

9. Safety

2 Applications

2.1 Construction and installation work schedule

2.2 List of requirements for materials and equipment

2.3 Schedule for the receipt of equipment and materials

Vzam. inv. No.

P.106.2015-PPR

OJSC "Vyksa Metallurgical Plant"

Kharlamov

Color Sorting Area Shelter

checked

metals. AUPS and SOUE.

general information

CJSC "AUTOMATIC"

LIST OF REFERENCES AND APPLIED DOCUMENTS

Designation

Name

Note

Reference Documents

123-FZ (as amended by

the federal law

"Technical

fire regulations

security"

GOST R ISO 9000-2008

Quality management systems.

Fundamentals and vocabulary

GOST R ISO 9001-2008

Quality management systems.

Requirements

GOST R ISO 9004-2010

Management for Success

organizations. Management based approach

quality

GOST R ISO 19011-2003

Systems Audit Guidelines

(ISO 19011-2003)

quality management and/or systems

environmental management

GOST R 40.003-2008

Certification system GOST R. Register of systems

quality. Management certification procedure

quality for compliance with GOST R ISO 9001-

2008 (ISO 9001:2008)

GOST 12.1.046-85. SSBT

Construction. Building lighting standards

sites

GOST 12.1.051-90. SSBT

Electrical safety. Safety distances

in the security zone of power lines

voltage over 1000 V

GOST 12.3.009-76*

Loading and unloading works.

General requirements security

GOST 12.3.010-82. SSBT

The container is industrial. Requirements

operational safety

GOST 12.3.020-80

The processes of movement of goods in enterprises.

General safety requirements

GOST 12.3.033-84. SSBT

construction machines. General requirements

operational safety

GOST R 12.4.026-2001.

Signal colors, safety signs and

signal marking. Appointment and rules

applications. General technical requirements and

characteristics. Test Methods

GOST 12.4.059-89. SSBT

Construction. Safety fences

inventory. General specifications

GOST 23407-78

Inventory building fences

sites and sites for the production of construction and

GOST 24258-88

Scaffolding tools.

General specifications

GOST 24259-80

Mounting accessories for temporary

fixing and alignment of building structures.

Classification and general technical requirements

GOST 26887-86

Platforms and stairs for construction

installation work. General specifications

GOST 27321-87

Rack-mounted scaffolding for construction

installation work. Specifications

GOST 28012-89

Scaffolding mobile collapsible.

Specifications

GOST 12.1.004-91*

Fire safety. General requirements

GOST 12.1.030-81. SSBT

Electrical safety. Protective ground.

Zeroing

GOST 12.1.033-81*

Fire safety.

Terms and Definitions

GOST 31251-2003

Building structures. Methods

definitions fire hazard

ST SEV 383-87

Fire safety in construction.

Terms and Definitions

SP 1.13130.2009

Escape routes and exits

SP 2.13130.2009

Fire protection systems.

Ensuring the fire resistance of protected objects

SP 3.13130.2009

Fire protection systems. System

alerts

and evacuation management

people in a fire. fire department requirements

security

SP 4.13130.2009

fire fighting systems

Limiting the spread of fire on

protection objects. requirements for volumetric

planning solutions

SP 5.13130.2009

fire fighting

Fire installations

signaling

automatic fire extinguishers. Norms and

design rules

SP 6.13130.2009

fire fighting systems

Electrical equipment. fire department requirements

security

SP 7.13130.2009

Heating,

Ventilation and air conditioning.

Fire requirements

SP 8.13130.2009

fire fighting systems

Sources of outdoor fire fighting

water supply. fire department requirements

security

SP 10.13130.2009

Fire protection systems.

Internal fire water supply.

Requirements fire safety

P.106.2015-PPR

SP 12-135-2003

Industry sample instructions for protection

SP 12-136-2002

Labor safety in construction.

Solutions for labor protection and industrial

security in organization projects

construction and work production projects

SNiP 12-01-2004

Organization of construction

SNiP 3.03.01-87

Bearing and enclosing structures

SNiP 12-03-2001

Labor safety in construction.

Part 1. General requirements

SNiP 12-04-2002

Labor safety in construction.

Part 2. Construction production

SNiP II-89-80*

Master plans for industrial

enterprises

SNiP 23-05-95*

natural and artificial lighting

PUE. Edition 7

Rules for the installation of electrical installations

MDS 12-19.2004

Construction mechanization. Exploitation

tower cranes in cramped conditions

lifting cranes.

Gosgortekhnadzor of Russia

Device rules and safe operation

load-lifting cranes-manipulators.

Gosgortekhnadzor of Russia

Rules for the device and safe operation

building hoists. Gosgortekhnadzor

Rules for the device and safe operation

lifts (towers).

Gosgortekhnadzor of Russia

POT RM-007-98

Intersectoral rules on labor protection at

loading and unloading operations and placement

POT RM-016-2001,

Intersectoral rules on labor protection

RD 153-34.0-03.150-00

(safety rules) during operation

electrical installations

Rules for the operation of electrical installations

consumers

STO NOSTROY 2.33.6-

Rules for preparing for acceptance and commissioning

operation of completed construction

STO NOSTROY 2.15.8-

residential buildings

internal. The device of local systems

P.106.2015-PPR

Requirements, rules and methods of control

STO NOSTROY 2.15.10-

Network engineering buildings and structures

internal. Security and fire systems

alarms, warning systems and

evacuation management, control systems and

access control, security systems

television. Assembly, commissioning

work and commissioning

STO NOSTROY 2.33.14-

Organization of construction production.

General provisions

STO NOSTROY 2.33.51-

Organization of construction production.

Preparation and production of construction and

installation work

STO NOSTROY 2.15.9-

"Engineering networks of buildings and structures

internal. The device of distributed systems

management. Installation, testing and adjustment.

Requirements, rules and control methods"

Attached documents

Appendix 1

Test program and methodology

AUPS and SOUE

Signature and date

P.106.2015-PPR

STATEMENT OF MAIN SETS OF WORKING DRAWINGS

Designation

Name

Note

G-21024-DS3-13-01-R-PS

PS and SOUE system

Signature and date

P.106.2015-PPR

Terms of reference for the design of fire safety systems in the organization of a site for the production of shredded scrap. Shelter of non-ferrous metals sorting zone.

Working documentation G-21024-DS3-13-01-R-PS "PS and SOUE system" developed by "Mosgipromez"

Requirements of regulatory documents approved in the prescribed manner

AT This section deals with the production of works on installation and commissioning of the automatic fire alarm system, warning system and management of people evacuation in case of fire.

Solutions for the production of works are aimed at achieving end result– commissioning of an object with necessary quality and within the stipulated time.

2. Characteristics of the object and construction conditions

Scrap metal recycling is a labor-intensive process that requires special equipment and preliminary sorting and classification of raw materials. As a result of processing, the quality of scrap is brought into line with existing standards in terms of composition, purity, dimensions, weight, density, crumbling and limiting content of alloying elements.

The OMK Casting and Rolling Complex (LPK, Vyksa District, Nizhny Novgorod Region, part of the United Metallurgical Company, CJSC OMK) plans to put into operation a shredded scrap production facility with a capacity of 1 million tons by the end of 2015. The project is one of the stages of the construction of the second stage of the timber complex. The equipment supplier is Metso Lindemann GmbH (Düsseldorf, Germany). The shredder plant is designed for crushing and cleaning scrap, sorting metal and eliminating non-metallic impurities.

Each fire compartment is provided independent systems supply and exhaust ventilation in accordance with the requirements of SNiP 2.04.05 - 91* and TU.

Possible source of fire (according to GOST 27331-87) - A1 Combustion of solids, accompanied by smoldering.

According to the reliability of power supply according to SP 31-110-2003, the entire facility as a whole belongs to category I.

The automatic installation of PS and SOUE protects the shelter room of the zone for sorting non-ferrous metals of the site for the production of shredded scrap.

Sheets of the need for materials and equipment for AUPS and SOUE, see the appendix (specifications).

Inv. no. Signature and date Mut. inv. No.

Automatic installation of a fire alarm and warning people about a fire is a set of fire alarm and warning systems designed to detect a fire, notify facility personnel and personnel about the presence of a fire and its location, to ensure the safe evacuation of people, launch automatic fire extinguishing equipment and ensure fire localization such as smoke extraction, ventilation, etc.

Composition of the fire alarm and warning system at the structural level:

central equipment, including a device for receiving alarm information (control and receiving devices, a control panel) and visualization tools;

system of sensors (detectors) of fire alarm;

devices for warning people about a fire, light and sound or speech;

equipment for alerting city services through the use of a telephone line and / or a radio transmitter;

start-up automation devices automatic system fire extinguishing, control of elevator equipment, ventilation and smoke removal.

3. Quality control

At all stages of work, it is necessary to carry out production quality control of construction and installation works, which includes incoming control working documentation, structures, products, materials and equipment, operational control of individual construction processes or production operations and acceptance control of intermediate and final work cycles. The composition of controlled indicators, the scope and methods of control must comply with the requirements of SNiP.

Quality control of construction and installation works should be carried out by specialists or special services equipped with technical means that ensure the necessary reliability and completeness of control.

During the input control of working documentation, its completeness and sufficiency of the technical information contained in it for the performance of work should be checked.

At the entrance control building structures, products, materials and equipment should be checked by external inspection for their compliance with the requirements of standards or other regulatory documents and working documentation, as well as the presence and content of passports, certificates and other accompanying documents. The results of the input control are recorded in the Logbook of the results of the input control in the form: GOST 24297-87, Appendix 1, to print the original form, see the Logbook of the results of the input control.

Operational control is carried out in the course of construction processes or production operations in order to ensure the timely detection of defects and the adoption of measures to eliminate and prevent them.

Inv. no. Signature and date Mut. inv. No.

The quality of work performance is ensured by the fulfillment of the requirements of the technical conditions for the production of work, compliance with the necessary technical sequence in the performance of interrelated work, and technical control over the progress of work.

During operational control, it is necessary to check compliance with the technology for performing construction and installation processes specified in the work production projects; compliance of the work performed with the working drawings, building codes and rules. Particular attention should be paid to the implementation of special measures during construction on subsiding soils, in areas with landslides and karst phenomena, permafrost, as well as during the construction of complex and unique objects.

Scheme of operational quality control of work

Composition of the operating room

control

Documentation

Compiler

geic

lingering

control

facilities

document

control

1. Availability of a certificate.

visually,

Before laying

Measurement Protocol

the control

2. Absence

megger

resistance

insulation damage.

isolation

3. Resistance measurement

cable insulation on

drum.

Operational

1. Mark, trace

th control

2. Compliance

gaskets

hidden works

cable laying

Acceptance

Boss

Resistance measurement

Megohmmeter

Protocol

the control

cable insulation

gaskets

resistance

isolation

The results of operational control are also recorded in the General work log.

Acceptance control is carried out to check and assess the quality of completed construction objects or their parts, as well as hidden works and individual critical structures.

The construction site must:

Keep a General work log, special logs for certain types of work, the list of which is established by the general contractor in agreement with subcontractors and the customer, and the Designer supervision log of design organizations.

Draw up certificates of inspection of hidden works, certificates of intermediate acceptance of critical structures, testing and testing of equipment, systems, networks and devices. Entries in the journals must be controlled by the customer and the representative of architectural supervision.

In accordance with articles 61 and 63 of the Rules of the fire regime in the Russian Federation, the heads of organizations are required to check the performance of fire protection systems, maintenance and preventive maintenance.

During scheduled and unscheduled inspections, employees of the state fire supervision of the Ministry of Emergency Situations of Russia check not only the availability of AUPS and SOUE systems, but also the existence of a maintenance contract with an organization that has a license from the Ministry of Emergency Situations and Maintenance and PPR Magazines.

Nowadays, trying to save money on various events related to technical security buildings, customers of this type of work force service companies to greatly reduce prices for these services, up to the formal existence of a contract without taking actual measures to maintain the system in working condition.

As they say: Works and works!

It seems that everything was formally observed, but more than once there were cases in the practice of inquiry into the facts of fires, that at the very moment when the fire alarm or warning system was out of order. fires happened. And further. of course, uncomfortable questions to the leadership followed, not to mention the consequences.

Even from the point of view of the benefit of the enterprise: it is cheaper to carry out monthly maintenance than in the event of a system breakdown, one-time payment of a large amount for its repair and restoration.

Like any job, maintenance requires labor. And with unreasonable price reduction Maintenance, it is clear that any company does not have the opportunity to carry out the full performance of work and everything is done somehow.

Each Manager of a serviced object wants to understand for himself not so much the subtleties and nuances of maintenance, but what he pays money for.

Let us consider below what activities are included in the monthly maintenance of the APS and SOUE and how this is done:

Control panel, Backup power supply:

    External inspection for the presence of light indication

    Open the backup power supply, measure the voltage of the battery, which should be (12V)

    Check incoming terminal blocks

    In case of non-compliance normal voltage replacement required

    Selectively disturb one of the ALs controlled by the control panel and make sure that the control panel operates in the “Alarm” mode. Inspection should show "Break". The indicator lights and the siren are flashing, the sounder is on

    Restore loop violations and set the control panel to standby mode

    Short-circuit the remote element of the controlled loop and make sure that the control panel operates in the “Alarm” mode Open the remote

    If the control panel has a backup power supply, disconnect the control panel from the mains leaving the voice power enable toggle switch on

    Switch off the control panel, disconnect the ohmmeter from the "Control" contacts and connect the monitoring station line to them

    Restore the control panel power circuit from the mains alternating current and cover the terminal blocks.

Low-current loops of fire systems:

    Checking the strength of fastening of mechanical protection points, entry points, passage points through the wall

    Inspection of insulation of wires and connections

    Wiping from various contaminants

    Taking the necessary measures, up to shutdown in case of emergency

    Elimination of sag in cable networks and damage to insulation

    Partial replacement of brackets and fasteners

    Replacement of areas with damage

    Changing parameters when disconnecting and connecting cable networks

Fire smoke detectors:

    Dust and dirt cleaning and external inspection

    Fastener tightening

    Checking the quality of fixing fittings

    Health check

    Inspection and elimination of visible damage

    Identification and repair of broken parts

Sound and voice annunciators:

    Check the condition of the loudspeaker

    Surface cleaning without dismantling the speech loudspeaker

    Restore the trunk to the radio node. Check loudspeaker power consumption setting

    Send a voice signal B-pillar radio communication node and make sure that the signal is audible at all points of the serviced premises.

    Make an entry in the maintenance work log, based on the results of the work.

These are the main activities that are performed monthly.

For each object, a plan is developed for the schedule of maintenance and preventive maintenance in accordance with the instructions of manufacturers and guidance documents.

You can order the service in St. Petersburg by contacting the Security Complex company.

I didn’t have five in the morning) I’m from the Far East .. thanks for the answer. We have a slightly different situation with municipalities. maintenance, of course, was carried out as you described, but for the second year almost 80% of the objects of education have been changed for maintenance and batteries, and how much money can we get from someone to replace the warning signs there (they stop shining, they are on), speakers, again detectors (to the question of what kind of animal Turquoise is - http://rovalant.com/production/biriu..., I'm glad that you didn't have to work with this device, the latest versions, by the way, have become more normal, errors have been fixed .. but on objects 98% of first-generation devices .. until recently, it was even impossible to read the configuration from them, and if you need to remove or deliver one detector, you had to program the entire object) and so, in fact, what we get, from all schools. gardens via the radio channel, alarm signals go immediately to the 01 console .. and a car immediately leaves .. if the school or kindergarten managed to call back right away - so they say and so - a false alarm, then it’s normal but they didn’t have time - the question arises who pays for the false call ?? and of course the most important question is who is to blame? there is only one answer from the firefighters - the service organization is to blame, since if you do the MOT correctly, then there will be no false alarms at all! for each such case, I write explanatory notes .. for example, today I was at school, the detector was installed in the exit vestibule .. the mountaineering section is engaged in the premises .. in the evening they have classes outside the door wide open .. the sensor is already covered with frost .. it worked at night! and explanations that the sensors work for humidity, dust in the same way as they do not work for smoke! what is the name of the detector? SMOKE means it only works on smoke. if it were DUST SMOKE WET then everything is clear! there are still moments such that spare parts should be at the facility 10%! never mind! the service organization is obliged at its own expense to change everything that breaks down and fails! in winter it reached the point of absurdity, the group in the kindergarten was flooded, under it in the group of the first floor 4-re PI was flooded, we change it at our own expense! the kindergarten refuses to pay, citing the fact that every month it pays us 1200 rubles, and everything is included in the cost of MOT! at the same time, one such addressable detector costs 1463 rubles! .. I tried from one school of a Trudovik (an intelligent man) to teach how to independently remove the alarm condition from the detector when a ladybug settled in it, a rural school had a disaster with these cows over the summer .. so the representative of the administration kicked me out of the office !! The operating organization is not supposed to know this! ! In general .. for myself, I made a simple conclusion, the administration, as always, wants everything to be but for free !! By the way. I remembered .. about the guarantees for PI, it is very interesting written in the passport! 1. Warranty period of operation is 24 months from the date of commissioning, but not more than 36 months from the date of issue, MTBF is not more than 10 years. and that's from the last 10 years!! we are clearly told - it is written 10 years, which means that it should work for 10 years and there can be no talk of any replacement! at the same time, the same passport says - RovalentSpetsProm LLC guarantees compliance technical CHARACTERISTICS DETECTOR, repair and replacement in
during the warranty period of operation, provided that the consumer observes the conditions of operation, storage and
transportation. Briefly expressed) it became easier!