Scheme of the formation of the signaling section that. State building codes of ukraine resource elemental estimated norms for commissioning
1. This section provides the norms of labor costs for commissioning works for independent alarm circuits (central, technological, local, emergency, warning, etc.), including light and sound signals, as well as electric network insulation control circuits.
2. The rates, in addition to those listed in clause 6 of the technical part, take into account the costs of the following commissioning work performed in accordance with the requirements of the rules for electrical installations, as well as SNiP 3.05.06-85 "Electrical devices":
testing and adjustment of relay-contactor equipment;
setting the time relay settings;
adjustment of flashing light devices;
testing devices and signaling schemes for operation.
3. The norms do not take into account and should be determined additionally according to the norms of other departments of the collection, the costs of commissioning for:
switching devices and their secondary switching circuits - in department 3;
wiring diagrams for signaling circuits - for department 6;
sensors, from which the signal enters the automatic control circuit - according to department 9;
high voltage tests - according to department 12.
4. In the composition of works according to the table. 1-146 includes checking the signaling circuits from the first intermediate terminal block of the devices that form the signal to the signaling section by creating a mode or their artificial imitation (in the absence of a signal implementation section, it is carried out directly to a light or sound signal).
5. In the composition of works according to the table. 1-147 includes setting up the alarm section equipment and ensuring the operation of light, sound and other alarms (including the RIS relay).
6. The standards of this section are calculated based on the conditions for the implementation of commissioning by a link with the following qualification composition:
Section 1. ALARM SCHEMES
Table 1-146Schemes for collecting and implementing information signals
Norm for 1 signal
Table 1-147
Schemes for the formation of a signaling section
Norm for 1 plot
Table 1-148
Mnemonic diagrams of the supervisory control panel
Norm for 1 scheme
Mnemonic diagram with the number of received signals |
|||||
Cost elements (resources) | Unit | before | for every 100 |
||
measurements | 50 | 100 | 200 | subsequent signals |
|
1-148-1 | 1-148-2 | 1-148-3 | 1-148-4 |
||
Labor costs of commissioning personnel | man-hour | 171 | 232 | 389 | 168 |
Introductory Instructions
1. This section contains prices for commissioning works for independent alarm circuits (central, technological, local, emergency, warning, etc.) including light and sound signals, as well as electric network insulation control circuits.
2. The prices take into account the costs of the following commissioning works, carried out in accordance with the requirements of the "Electrical Installation Rules", as well as SNiP 3.05.06-85 "Electrical Devices":
check and adjustment of relays and equipment;
adjustment of flashing light devices;
testing devices and signaling schemes for operation.
3. The prices do not take into account and should be determined additionally according to the prices of other departments of the Collection, the costs of commissioning for:
switching devices and their secondary switching circuits - in department 03;
wiring diagrams for signaling circuits - in department 06;
sensors, from which the signal enters the automatic control circuit - according to department 09;
high voltage tests according to department 12.
Rate code | Labor costs, man-hour |
||
Section 1. ALARM SCHEMES Table Schemes for collecting and implementing information signals Meter: Signal |
|||
Collection and implementation of information signals of protection devices, automation of electrical and technological modes | |||
Table Schemes for the formation of the signaling section Meter: plot |
|||
The scheme of formation of the signaling section (central, technological, local, emergency, warning, etc.) | |||
Table Mimic diagrams of the supervisory control panel Meter: scheme (prices from 01 to 03); 100 signals (price 04) |
|||
Mnemonic diagram of the supervisory control panel with the number of received signals up to: | |||
for every 100 subsequent signals add to the price 03 | |||
Section 2. ELECTRICAL NETWORK INSULATION CONTROL SCHEMES Table Electric network insulation control scheme Meter: circuit |
|||
Control circuit: | |||
using electrical measuring instruments | |||
with the use of relay-contactor equipment and non-contact elements |
SECTION 11. MEASUREMENTS IN ELECTRICAL INSTALLATIONS
Introductory Instructions
1. This section contains prices for special tests and measurements in the course of work on electrical cables and electrical installations.
2. The prices take into account labor costs for the following commissioning works, performed in accordance with the requirements of the "Electrical Installation Rules", as well as SNiP 3.05.06-85 "Electrical Devices":
choice of measurement method;
assembly and disassembly of test circuits;
ensuring special safety measures at the test (measurement) object;
measurement production.
3. Prices from 2 to 5, 1, 1 take into account the costs of installing auxiliary electrodes and their connection to measuring instruments and the measured object.
4. Rates table. applies only to electrical machines and apparatus installed in power circuits.
5. For this section, prices for commissioning works are determined that are not taken into account by prices for other departments of the Collection.
6. Price 1 takes into account the costs of performing work for a three-wire line. For a two-wire or four-wire line, the price should be determined at a price of 1 with a coefficient of 0.7 and 1.3, respectively.
Rate code | Name and technical specifications equipment | Direct costs (compensation of commissioning personnel), rub. | Labor costs, man-hour |
Section 1. CABLE WORK Table Search and location of cable damage with burning Meter:I cable (prices 01 and 02); 500 m cable (price 3) |
|||
Search and determination of the location of cable damage with burning, cable length, m, up to: | |||
for each subsequent 500 m add to the price 02 | |||
Table Determination of active resistance or working electrical capacitance of a cable core Meter: 1 measurement |
|||
Determination of active resistance or working electrical capacitance of a cable core for voltage, kV, up to: | |||
Section 2. GROUNDING DEVICES Table Measurement of resistance to current spreading Meter: 1 measurement |
|||
Current flow resistance measurement: | |||
ground electrode | |||
contour with a diagonal, m, up to: | |||
Table Checking the presence of a circuit between grounding conductors and grounded elements Measuring points |
|||
Checking the presence of a circuit between grounding conductors and grounded elements | |||
Table Determination of soil resistivity Meter: 1 measurement |
|||
Determination of soil resistivity | |||
Table Measurement of the impedance of the phase-zero circuit Meter: 1 pantograph |
|||
Measurement of the impedance of the "phase-zero" circuit | |||
Table Characterization for determining the contact voltage Meter: 1 touch point |
|||
Characterization for determining the touch voltage at the points specified in the project, in networks with a voltage of over. 1 kV | |||
Measurement of touch voltage in 380/220 V networks with solidly grounded neutral | |||
Section 3. OTHER MEASUREMENTS Table Measurement of the dielectric loss tangent Meter: 1 measurement |
|||
Measurement of the dielectric loss tangent | |||
Table Transition resistance measurement direct current Meter: 1 measurement |
|||
Measurement of transient resistance to direct current of the contacts of the busbars of distribution devices with voltage, kV, up to: | |||
Table Measurement of active, inductive resistances, capacitance of electrical machines and devices Meter: 1 measurement |
|||
Measurement of active, inductive resistance and capacitance of electrical machines and devices | |||
Table Characterization Gauge: 1 characteristic |
|||
Removal of characteristics of switching devices: | |||
temporary | |||
high-speed | |||
Table Phasing of an electric line or transformer Meter: 1 phasing |
|||
Phasing of an electric line or transformer with a voltage network, kV: | |||
Table Measurement of absorption coefficient and non-linearity of insulation Meter: 1 measurement |
|||
Coefficient measurement: | |||
winding absorption of transformers and electrical machines | |||
non-linearity of electrical machine insulation | |||
Table Acquisition of oscillograms and vector diagrams Meter:I oscillogram (price 01); 1 diagram (price 02) |
|||
Removal, processing and analysis: | |||
oscillograms | |||
vector diagrams | |||
Table Measurement of leakage currents or breakdown voltage |
11 DEVICES AND ALARM CIRCUIT
11.1 Introductory notes
11.1.1 This section provides labor costs for commissioning for independent alarm circuits (central, technological, local, emergency, warning, etc.), including light and sound signals, as well as electric network insulation control circuits. 11.1.2 In norms other than those listed in clause 1.6 the technical part, the costs for the following commissioning works, carried out in accordance with the requirements of the Rules for Electrical Installations, as well as SNiP 3.05.06-85 "Electrical Devices", are taken into account: - checking and configuring relay-contactor and non-contact equipment; - setting the time relay settings; - adjustment of flashing light devices; - testing devices and signaling schemes for operation.11.1.3. The norms do not take into account and should be determined additionally according to the norms of other sections of the Collection, the costs of commissioning for: - switching devices and their secondary switching circuits -according to the norms groups 15 to 19; - signaling circuit wiring diagrams - according to the norms of groups 41 to 42; - sensors, from which the signal enters the automatic control circuit, - according to the norms of groups 51 to 53; - tests with increased voltage - according to the standards of group 71. 11.1.4 The scope of work according to the norm 1-58-1 includes checking the signaling circuits from the first intermediate terminal block of signal-generating devices to the signaling section by creating modes or their artificial imitation (with in the absence of a site for the implementation of signals, it is carried out directly on a light or sound signal). 11.1.5 The scope of work in accordance with the norm 1-58-2 includes setting up the equipment of the signaling section and ensuring the functioning of light, sound and other signaling (including the RIS relay).
Group 58 Signaling schemes
Meter: signal (standard 1-58-1); plot (norm 1-58-2); scheme (standards 1-58-3 - 1-58-6, 1-59-1, 1-59-2). Group 58 (standards 1 to 6) Resource name | unit of measurement | Scheme for collecting and implementing information signals of protection devices, automation of electrical and technological modes | The scheme for the formation of the signaling section (central, technological, local, emergency, warning, etc.) | Mnemonic diagram of the supervisory control panel with the number of received signals |
|||
for every 100 subsequent signals |
|||||||
Group 59 Electric network insulation monitoring schemes
Gauge: Schematic Group 59 (Norms 1 to 2) Resource name | unit of measurement | Control scheme |
|
using electrical measuring instruments | with the use of relay-contactor equipment and non-contact elements |
||
Labor costs of commissioning personnel |
12 MEASUREMENTS IN ELECTRICAL INSTALLATIONS
12.1 Introductory notes
12.1.1 This section provides labor costs for testing and measuring in electrical installations and on electrical cables in accordance with the requirements of the Rules for the Installation of Electrical Installations, SNiP 3.05.06-85 "Electrical Devices", as well as the "Rules of Technical operation (PTE) of electrical installations of consumers” and “Safety Rules for the operation of electrical installations of consumers” (1998, Kyiv). 12.1.2 This section contains the cost rates for work not included in the commissioning work of other sections of the Collection, as well as for repeated measurements. 12.1.3 In norms other than those listed in clause 1.6 works listed in clause 1.5 the technical part of the Collection takes into account labor costs for the following commissioning works: - selection of the measurement method; - assembly and disassembly of test and measurement circuits; - ensuring measures for labor protection at the object of testing (measurement); - production of measurements.12.1.4 The standards from 1-61-1 to 1-61-5, 1-61-7, 1-61-9 take into account labor costs for the installation of auxiliary electrodes and their connection to measuring instruments and measured objects. 12.1.5 Labor costs for measuring the insulation resistance of electrical machines, transformers, switching devices, protection and automation devices, voltage and control current circuits, static converters, as well as devices for automatic control systems for electric drives are taken into account in the standards for setting up the apparatuses, devices and control systems listed above according to the relevant sections of this Collection and additionally according to this section are not determined.
Group 60 Cable work
Meter: cable (standards 1-60-1 - 1-60-3); measurement (standards 1-60-4, 1-60-5)Group 60 (rates 1 to 5)
Resource name | unit of measurement | Search and determination of the location of damage to a cable with a live, cable length, m | Determination of active resistance or working electrical capacitance of a cable core at voltage, kV |
|||
for each subsequent 500 m | ||||||
Group 61 Earthing devices
Meter: measurement (standards 1-61-1 - 1-61-5, 1-61-7); 100 points (norm 1-61-6); pantograph (standard 1-61-8); touch point (1-61-9)Group 61 (rates 1 to 5)
Resource name | unit of measurement | Current flow resistance measurement |
||||
ground electrode | contour with a diagonal, m |
|||||
Labor costs of commissioning personnel |
End of group 61 (norms 6 to 9)
Resource name | unit of measurement | Checking the presence of a circuit between grounding conductors and grounded elements | Determination of soil resistivity | Measurement of the impedance of the "phase-zero" circuit | Characterization for determining the touch voltage at the points specified in the project |
Labor costs of commissioning personnel |
Group 62 Other measurements
Meter: measurement (standards 1-62-1 - 1-62-5, 1-62-7, 1-62-10, 1-62-11, 1-62-14, 1-62-16); characteristic (norm 1-62-6); phasing (norms 1-62-8, 1-62-9); oscillogram (standard 1-62-12); diagram (norm 1-62-13); line (norm 1-62-15); test (standards 1-62-17, 1-62-18). Group 62 (standards 1 to 5) Resource name | unit of measurement | Measurement of the tangent of the dielectric loss angle | Measurement of DC transient resistance of busbar contacts of distribution devices with voltage, kV | Measurement of active, inductive resistance and capacitance of electrical machines and devices |
||
Labor costs of commissioning personnel | ||||||
Note. Norm 1-62-5 applies only to electrical machines and devices installed in power circuits. |
Continuation of group 62 (norms 6 to 10)
Resource name | unit of measurement | Removal of temporary characteristics-teri-stick | Removal of speed characteristics of switching devices | Phasing of electric line or transformer with mains voltage, kV | Measurement of the absorption coefficient (P60 / P15) of the windings of transformers and electrical machines |
|
Labor costs of commissioning personnel |
Resource name | unit of measurement | Measuring the coefficient of non-linearity of the insulation of an electrical machine | Removal, processing and analysis of oscillograms | Removal and analysis of vector diagrams | Measurement of leakage currents or breakdown voltage of an arrester or leakage currents of a voltage limiter |
Labor costs of commissioning personnel |
Resource name | unit of measurement | Measurement of insulation resistance with a megohmmeter | Free flow test of transformer oil and measurement of impregnation coefficient of low pressure cable lines (hydraulic and impregnation tests) | Breakdown oil test |
|
cable and other lines with voltage up to 1 kV, intended for the transmission of electricity to distribution devices, shields, cabinets and switching devices | winding machines, apparatus and wires |
||||
Labor costs of commissioning personnel 1.1 This Collection contains resource elemental estimated norms for commissioning (RESNpn), necessary to determine the need for labor costs when performing commissioning for refrigeration, compressor and carbon dioxide Rules for determining the cost of construction dbn d 1-1-2000, as amended in accordance with Addendum No. 3, approved by order (1)Document2.12 ADDITIONAL REQUIREMENTS FOR THE DEVELOPMENT OF ESTIMATE DOCUMENTATION FOR EXPANSION, RECONSTRUCTION AND TECHNICAL RE-EQUIPMENT OF ENTERPRISES, BUILDINGS AND FACILITIES 30 |
Download(direct link) : posobieposostavleniusmetnih2005.djvu Previous 1 .. 58 > .. >> Next
technological parameters and mutual control of operating modes.
Technological complex, including units in the amount of up to 10
pcs."1set*
01-13-030-0G1 "Centralized (dispatch) control systems
areas included in the common technological complex. Technological
a complex that includes managed plots in the amount of up to 5
pcs.set*
11.1.9. Estimate No. 9. Initial data
Yu """ BUS SYSTEM 10KV" "9" COMMISSIONING OF ELECTRICAL EQUIPMENT AND
FOR RZA DEVICES "FEDERAL UNIT PRICES FOR COMMISSIONING
FERp-2001. COLLECTION N1. ELECTRICAL DEVICES. TYPICAL DIAGRAM (OR
CODE OF A SPECIFIC SCHEME)" *
148
Note line (P) indicates:
P ADJUSTMENT WORKS. THE ESTIMATE INCLUDES OVERHEAD COST RATES 65% (MDS 81
-33.2004.APP.4.P48), ESTIMATED PROFIT 60% (MDS-25.2001
.APP.3,P48).OP.2.1 .T1 .P5. PERFORMANCE OF COMMISSIONING WORKS IN
ELECTRICAL INSTALLATIONS THAT ARE UNDER VOLTAGE WITH DESIGN
OF THE PERMIT OR INSTRUCTION COEFFICIENT 1.3 FOR 85% OF THE COST К= 1.255
(K \u003d 1 + 0.3.0.85 \u003d 1.255).
INSTALLATION WORKS CARRIED OUT WITH ATTRACTION OF FUNDS OF THE FEDERAL BUDGET,
IN THE CITY OF MOSCOW TO THE PRICES OF FER-2001. INTRODUCED BY A LETTER OF THE RF GOSSTROY
FOR DECEMBER 2004 (K=4.98)*
01-03-002-04 "2" Three-pole switch with voltage up to 1 kV
electromagnetic, thermal or combined release, rated
current up to 50 A "pcs. *
01-04-034-02"1 "Complete protection and automation devices of the SPAC-series
800"set*
01 -04-063-0 And "Arc protection of sections of complete distribution
devices (KRU) "set *
01-05-023-02 "1" ACR device with subsequent automatic reclosure after restoration
frequency"device*
01-06-020-03 "2" Secondary circuits of the voltage transformer three-
phase "system *
01 -06-021-01"2"Wiring diagram of a three-wire system with the number
panels (cabinets, cells) up to 2 "scheme *
01-06-021-02 "2" Wiring diagram of a three-wire system, for each
01-06-021-0Г5 "Wiring diagram of a three-wire system with the number of panels
(cabinets, cells) up to 2 "scheme *
01-06-021-02 "65" Wiring diagram of a three-wire system, for each
subsequent panel (cabinet, cell) over 2 "scheme *
01-06-022-01"5"Scheme of redundant power supply of a three-wire system from
other power supply with manual switch device"-diagram*
01 -06-023-01 "1 "Voltage level control device for AC or
rectified operational current "device *
01 -09-001-01 "3" Contact mechanical sensor with the number of control circuits
up to 2"*
01-09-010-03 "1" Relay contactor control functional group with
the total number of external interlocking connections up to Yu "pcs. *
149
A guide to the preparation of estimates (estimates)
for commissioning of electrical devices
Z "pcs. *
01-09-002-01 "3" Non-contact analog sensor with "input-output" number up to
Z "pcs. *
01-09-011-02 "2" Functional control group analog non-contact
with a total number of elements and settings up to 5 "pcs. *
01-10-001-01 "12" Collection and implementation of information signals of protection devices,
01-10-002-01 "4" Scheme of formation of the signaling section (central,
technological, local, emergency, preventive, etc.) "section *
01-10-003-01 "G" Mnemonic diagram of the dispatch control board with the number
received signals up to 50 "circuit *
01-10-010-01 "G" Scheme for monitoring the insulation of the electrical network using
electrical measuring instruments "diagram *
01-10-010-02"1 "Scheme for monitoring the insulation of an electrical network using
relay-contactor equipment and non-contact elements - diagram *
01-10-001-01 "15" Collection and implementation of information signals of protection devices,
automation of electrical and technological modes "signal *
01-10-001-01 "6" Collection and implementation of information signals of protection devices,
automation of electrical and technological modes "signal *
The following rates are applied with coefficient K=1.255, for payment and
labor costs:
01-02-016-02 "1" Three-phase voltage transformer with voltage up to 11
kV "pcs. *
01-11-010-03"1"Measurement of resistance to current spreading of the circuit with
diagonal, m, up to 200 "1meas. *
01-11-011-0G0.82 "Checking the presence of a circuit between grounding and grounded
elements"YPoint*
01-11-024-02 "6" Phasing of an electric line or transformer with a network
voltage, kV, St. 1"1phase*
01-11-026-02"12"Removal, processing and analysis of vector diagrams"1diagram*
01-11-028-01 "2" Insulation resistance measurement with a megohmmeter of cable and
other lines with voltage up to 1 kV intended for transmission
electricity to switchgears, shields, cabinets,
switching devices and electrical consumers "1 line*
150
"Mo-" ¦ Off."
A guide to the preparation of estimates (estimates)
Table 1-143
Functional control groups analog?? contactless
Norms for 1 pc.
Table 1-144
Functional control groups discrete?? contactless
Norms for 1 pc.
Table 1-145
Circuits of automatic control systems
Norms for 1 pc.
SECTION 10. DEVICES AND SIGNALING CIRCUITS
Introductory Instructions
1. This section provides the labor costs for commissioning for independent signaling circuits (central, technological, local, emergency, warning, etc.), including light and sound signals, as well as electric network insulation monitoring circuits.
2. The rates, in addition to those listed in clause 6 of the technical part, take into account the costs of the following commissioning work performed in accordance with the requirements of the rules for electrical installations, as well as SNiP 3.05.06-85 "Electrical devices":
testing and adjustment of relay-contactor equipment;
setting the time relay settings;
adjustment of flashing light devices;
testing devices and signaling schemes for operation.
3. The norms do not take into account and should be determined additionally according to the norms of other departments of the collection, the costs of commissioning for:
switching devices and their secondary switching circuits - in department 3;
wiring diagrams for signaling circuits - for department 6;
sensors, from which the signal enters the automatic control circuit - according to department 9;
high voltage tests - according to department 12.
4. In the composition of works according to the table. 1-146 includes checking the signaling circuits from the first intermediate terminal block of the devices that form the signal to the signaling section by creating a mode or their artificial imitation (in the absence of a signal implementation section, it is carried out directly to a light or sound signal).
5. In the composition of works according to the table. 1-147 includes setting up the alarm section equipment and ensuring the operation of light, sound and other alarms (including the RIS relay).
6. The standards of this section are calculated based on the conditions for the implementation of commissioning by a link with the following qualification composition:
Section 1. ALARM SCHEMES
Table 1-146
Schemes for collecting and implementing information signals
Norm for 1 signal
Table 1-147
Schemes for the formation of a signaling section
Norm for 1 plot
Table 1-148
Mnemonic diagrams of the supervisory control panel
Norm for 1 scheme
Section 2. ELECTRICAL NETWORK INSULATION CONTROL SCHEMES
Table 1-149
Electric network insulation control schemes
Norm for 1 scheme
SECTION 11. MEASUREMENTS IN ELECTRICAL INSTALLATIONS
Introductory Instructions
1. This section provides labor costs for testing and measuring in electrical installations and on electric cables in accordance with the requirements of the rules for the installation of electrical installations, SNiP 3.05.06-85 "Electrical devices", as well as the "Rules for technical operation (PTE) of electrical installations of consumers" and "Safety regulations for electrical installations of consumers".
2. This section contains the cost rates for work that was not included in the commissioning work of other departments of the collection, as well as for repeated measurements.
3. The rates, in addition to those listed in paragraph 6 of the technical part, take into account labor costs for the following commissioning:
choice of measurement method;
assembly and disassembly of test and measurement circuits;
ensuring safety measures at the test object (measurement);
measurement production.
4. In the norms from 1-152-2 to 1-152-5, 1-154-1, 1-156-1, labor costs for the installation of auxiliary electrodes and their connection with measuring instruments and measured objects.
5. Labor costs for measuring the insulation resistance of electrical machines, transformers, switching devices, relay protection and automation devices, voltage and operating current circuits, static converters, as well as devices for automatic control systems for electric drives are taken into account in the standards for setting up the above devices, devices and control systems for the relevant sections of this collection and additionally for this section 11 are not determined.
Labor costs for measuring the insulation resistance of control cables between consoles, panels, cabinets, control stations, as well as between individual devices are taken into account in the commissioning standards:
functional groups as part of automatic control and regulation systems - in department 9;
secondary switching circuits of power plants and substations - according to the relevant sections of this collection.
Additionally, according to this section, labor costs for these works are not determined.
6. Labor costs for measuring the insulation resistance of power wiring from the starting device to the current collector are determined in the following order:
if the pantograph is an electric motor or a solenoid, then labor costs are taken into account by the norm for commissioning for the specified equipment in department 7 and are not additionally determined in department 11;
if the current collector is a transformer or other electrical apparatus included in the nomenclature of this collection, then labor costs are taken into account by the commissioning standards in department 2 and are not additionally determined in department 11;
if the current collector is an active resistance or other electrical apparatus not included in the nomenclature of this collection, then labor costs should be determined according to the norm 1-163-1 of this department;
for power wiring from the cabinet to the starting device (line), labor costs should also be determined according to the norm 1-163-1.
7. The standards of this section are calculated on the basis of the conditions for the implementation of commissioning by a link with the following qualification composition:
Section 1. CABLE WORK
Table 1-150
Search and determination of the location of cable damage with burning
Norms for 1 cable
Table 1-151
Determination of active resistance or working
electric capacitance of the cable core
Norms for 1 measurement
Section 2. GROUNDING DEVICES
Table 1-152
Current spreading resistance measurements
Norms for 1 measurement
Table 1-153
Checking the presence of a circuit between grounding conductors
and earthed elements
Norm per 100 points
Table 1-154
Determination of soil resistivity
Norm for 1 measurement