The composition of the heating project. Spds

GOST 21.602-2003

GOST 21.602-2003
INTERSTATE STANDARD
PROJECT DOCUMENTATION SYSTEM
FOR CONSTRUCTION
RULES OF PERFORMANCE

INTERSTATE SCIENTIFIC AND TECHNICAL COMMISSION
FOR STANDARDIZATION AND TECHNICAL REGULATION
IN CONSTRUCTION (MNTKS)
MOSCOW
Foreword

1 DEVELOPED by the Federal State Unitary Enterprise "Design, Design and Research Institute "SantekhNIIproject"" (FSUE SantekhNIIproekt) and the Federal State Unitary Enterprise "Center for the Methodology of Rationing and Standardization in Construction" (FSUE CNS)
INTRODUCED by Gosstroy of Russia
2 ADOPTED by the Interstate Scientific and Technical Commission for Standardization and Technical Regulation in Construction on October 18, 2002
Voted for the adoption of the standard:
Name of the state Name of the state construction management body
Azerbaijan Republic Gosstroy of the Azerbaijan Republic
Republic of Armenia Ministry of Urban Development of the Republic of Armenia
Republic of Kazakhstan Kazstroykomitet
Kyrgyz Republic State Commission for Architecture and Construction under the Government of the Kyrgyz Republic
Republic of Moldova Ministry of Ecology, Construction and Territorial Development of the Republic of Moldova
Russian Federation Gosstroy of Russia
Republic of Tajikistan Komarchstroy of the Republic of Tajikistan
Republic of Uzbekistan Goskomarchitektstroy of the Republic of Uzbekistan Ukraine Gosstroy of Ukraine
3 INSTEAD OF GOST 21.602-79
4 INTRODUCED from June 1, 2003 as the state standard of the Russian Federation by the Decree of the Gosstroy of Russia dated May 20, 2003 No. 39
CONTENT
1 Scope 2
2 Normative references 2
3 Definitions 3
4 General provisions 3
5 General data on working drawings 7
6 System drawings 13
7 System installation drawings 21
8 Sketch drawings of general views of non-standard products 23
9 Specification of equipment, products and materials 23
10 Questionnaires and dimensional drawings 24
Annex A Terms used in this standard 25
Appendix B An example of the implementation of a layout plan for placing installations of systems 26
Annex B Examples of implementation of plans and sections of drawings of systems 26
Appendix D Examples of implementation of schemes for heating and heat supply systems 29
Appendix E Examples of implementation of schemes of ventilation systems 32
Annex E Examples of implementation of plans and sections of drawings of installations of systems 34
Annex G An example of drawing up a specification for equipment, products and materials 36
GOST 21.602-2003
INTERSTATE STANDARD
System of design documents for construction
RULES OF PERFORMANCE
HEATING WORKING DOCUMENTATION,
VENTILATION AND AIR CONDITIONING
System of design documents for construction.
Rules for execution of working documentation of heating, ventilation
and air conditioning
Introduction date 2003-06-01
1 area of ​​use
This standard establishes the composition and rules for the design of working documentation for heating, ventilation and air conditioning systems for buildings and structures for various purposes.
2 Normative references
This standard uses references to the following standards:
GOST 2.316-68 ESKD. Rules for applying inscriptions, technical requirements and tables on drawings
GOST 2.782-96 ESKD. Conditional graphic designations. Hydraulic and pneumatic machines
GOST 2.785-70 ESKD. Conditional graphic designations. Pipe fittings
GOST 21.101-97 SPDS. Basic requirements for design and working documentation
GOST 21.110-95 SPDS. Rules for the implementation of the specification of equipment, products and materials
GOST 21.112-87 SPDS. Handling equipment. Conditional images
GOST 21.114-95 SPDS. Rules for the implementation of sketch drawings of general views of non-standard products
GOST 21.205-93 SPDS. Symbols of elements of sanitary systems
GOST 21.206-93 SPDS. Symbols of pipelines
GOST 21.404-85 SPDS. Automation of technological processes. Conventional designations of devices and automation equipment in diagrams
GOST 21.501-93 SPDS. Rules for the implementation of architectural and construction working drawings
GOST 3262-75 Steel water and gas pipes. Specifications
3 Definitions
The following definitions apply in this standard:
3.1 system: A complex of functionally interconnected equipment, installations (blocks), devices, products, pipelines and (or) air ducts (for example, supply system P1, exhaust system V1, heating system 1, heat supply system for installations P1 - P3).
3.2 drawing of systems: A drawing that defines the relative location of functionally interconnected equipment, installations (units), pipelines and (or) air ducts and other parts of the designed systems.
3.3 installation: The conventional name of the complex of interconnected equipment and (or) devices, and, if necessary, pipelines (air ducts) connected to the system installation equipment (for example, installation of the supply system P1, installation of the exhaust system B1).
3.4 installation drawing: A drawing containing a simplified representation of installations, defining their design, dimensions, relative position and designation of installation elements and other necessary data.
3.5 The terms used in this standard according to GOST 21.110 and GOST 21.114 are given in Appendix A.
4 General provisions
4.1 Working documentation for heating, ventilation and air conditioning is carried out in accordance with the requirements of this standard, GOST 21.101 and other related standards of the Design Documentation System for Construction (SPDS).
4.2 The composition of the working documentation of heating, ventilation and air conditioning systems (hereinafter referred to as systems) includes:
- working drawings intended for the production of construction and installation works (the main set of working drawings of the OB grade);
- sketch drawings of general views of non-standard products, structures, devices, mounting blocks (hereinafter - sketch drawings of general views of non-standard products);
- specification of equipment, products and materials;
- Questionnaires and dimensional drawings*;
- local estimate*.
* Perform if necessary.
4.3 The composition of the main set of working drawings of the grade OV includes:
- general data on working drawings;
- drawings (plans, sections and diagrams) of systems;
- drawings (plans and sections) of system installations.
The composition of the main set of working drawings of the OB grade is also allowed to include working drawings of heating points with a coolant input diameter of up to 150 mm.
4.4 Each system is assigned a designation consisting of a brand (table 1) and a serial number of the system within the brand.
Example - P1, P2.
System installations are assigned the same designations as the systems they belong to.
4.5 Elements of heating systems are assigned designations consisting of a brand (table 2) and the serial number of the element within the brand.
Example - St1, St2.
It is allowed to index the risers of heating systems in capital letters within the designation of the riser.
Example - St2A, St2B.
Table 1

GOST 602-2003

Group G01

INTERSTATE STANDARD

System of design documents for construction

RULES FOR THE IMPLEMENTATION OF WORKING DOCUMENTATION

HEATING, VENTILATION AND AIR CONDITIONING

System of design documents for construction.

Rules for execution of working documentation of heating,

ventilation and air conditioning

OKS 01.100.30

OKSTU 0021

Introduction date 2003-06-01

Foreword

1 DEVELOPED by the Federal State Unitary Enterprise "Design, Design and Research Institute" SantekhNIIproekt "(FSUE SantekhNIIproekt) and the Federal State Unitary Enterprise" Center for Methodology, Rationing and Standardization in Construction "(FSUE CNS)

INTRODUCED by Gosstroy of Russia

2 ADOPTED by the Interstate Scientific and Technical Commission for Standardization and Technical Regulation in Construction on October 18, 2002

State name

Name of the public administration body for construction

The Republic of Azerbaijan

Gosstroy of the Republic of Azerbaijan

Republic of Armenia

Ministry of Urban Development of the Republic of Armenia

The Republic of Kazakhstan

Kazstroycommittee

Republic of Kyrgyzstan

State Commission for Architecture and Construction under the Government of the Kyrgyz Republic

The Republic of Moldova

Ministry of Ecology, Construction and Territorial Development of the Republic of Moldova

Russian Federation

Gosstroy of Russia

The Republic of Tajikistan

Komarchstroy of the Republic of Tajikistan

The Republic of Uzbekistan

Goskomarchitektstroy of the Republic of Uzbekistan

Ukraine

Gosstroy of Ukraine

3 INSTEAD OF GOST 21.602-79

4 INTRODUCED from June 1, 2003 as the state standard of the Russian Federation by the Decree of the Gosstroy of Russia dated May 20, 2003 N 39

A misprint was made by the legal bureau "Kodeks"

1 area of ​​use

This standard establishes the composition and rules for the design of working documentation for heating, ventilation and air conditioning systems for buildings and structures for various purposes.

This standard uses references to the following standards:

GOST 2.316-68 ESKD. Rules for applying inscriptions, technical requirements and tables on drawings

GOST 2.782-96 ESKD. Conditional graphic designations. Hydraulic and pneumatic machines

GOST 2.785-70 ESKD. Conditional graphic designations. Pipe fittings

GOST 21.101-97 SPDS. Basic requirements for design and working documentation

GOST 21.110-95 SPDS. Rules for the implementation of the specification of equipment, products and materials

GOST 21.112-87 SPDS. Handling equipment. Conditional images

GOST 21.114-95 SPDS. Rules for the implementation of sketch drawings of general views of non-standard products

GOST 21.205-93 SPDS. Symbols of elements of sanitary systems

GOST 21.206-93 SPDS. Symbols of pipelines

GOST 21.404-85 SPDS. Automation of technological processes. Conventional designations of devices and automation equipment in diagrams

GOST 21.501-93 SPDS. Rules for the implementation of architectural and construction working drawings

GOST 3262-75 Steel water and gas pipes. Specifications

3 Definitions

The following definitions apply in this standard:

3.1 system: A complex of functionally interconnected equipment, installations (blocks), devices, products, pipelines and (or) air ducts (for example, supply system P1, exhaust system V1, heating system 1, heat supply system for installations P1-P3).

3.2 systems drawing: A drawing that determines the relative location of functionally interconnected equipment, installations (units), pipelines and (or) air ducts and other parts of the designed systems.

3.3 installation: Conditional name of the complex of interconnected equipment and (or) devices, and, if necessary, pipelines (air ducts) connected to the equipment of the system installation (for example, installation of the supply system P1, installation of the exhaust system B1).

3.4 installation drawing: A drawing containing a simplified image of the installations, defining their design, dimensions, relative position and designation of the elements of the installations and other necessary data.

3.5 The terms used in this standard according to GOST 21.110 and GOST 21.114 are given in Appendix A.

4 General provisions

4.1 Working documentation for heating, ventilation and air conditioning is carried out in accordance with the requirements of this standard, GOST 21.101 and other related standards of the Design Documentation System for Construction (SPDS).

4.2 The composition of the working documentation of heating, ventilation and air conditioning systems (hereinafter referred to as systems) includes:

Working drawings intended for the production of construction and installation works (the main set of working drawings of the OB grade);

Sketch drawings of general views of non-standard products, structures, devices, mounting blocks (hereinafter - sketch drawings of general views of non-standard products);

Specification of equipment, products and materials;

Questionnaires and dimensional drawings*;

_________________

Local estimate*.

_________________

* Perform as needed

4.3 The composition of the main set of working drawings of the grade OV includes:

General data on working drawings;

Drawings (plans, sections and diagrams) of systems;

Drawings (plans and sections) of system installations.

The composition of the main set of working drawings of the OB grade is also allowed to include working drawings of heating points with a coolant input diameter of up to 150 mm.

4.4 Each system is assigned a designation consisting of a brand (table 1) and a serial number of the system within the brand.

Table 1

Name of systems and installations of systems

brand

With mechanical prompting:

supply systems, system installations

exhaust systems, system installations

air curtains

heating units

With a natural urge:

supply systems

PE

exhaust systems

BE

Example - P1, P2.

System installations are assigned the same designations as the systems they belong to.

4.5 Elements of heating systems are assigned designations consisting of a brand (table 2) and the serial number of the element within the brand.

table 2

Example - St1, St2.

It is allowed to index the risers of heating systems in capital letters within the designation of the riser.

Example - St2A, St2B.

4.6 Hatches for measuring air parameters are marked with the brand "LP", hatches for cleaning air ducts - with the brand "LV".

4.7 Pipelines and their elements in the drawings are indicated by conventional graphic symbols and (or) simplified images in accordance with GOST 21.206. When performing pipelines, in a simplified way, as a rule, the general designations provided for by GOST 21.206 are used (table 1, paragraphs 6a and 7a).

Graphic designations of individual elements of pipelines (an isolated section of a pipeline, a pipeline in a pipe (case), a pipeline in an stuffing box, a water seal, a compensator, a shock-absorbing insert, a place of resistance in the pipeline (throttle washer), a support (suspension) of the pipeline) are taken according to Table 6 GOST 21.205.

Alphanumeric designations of pipelines are taken according to table 8 of GOST 21.205.

4.8 Graphic designations of elements of general use (filter, heater, cooler, heat exchanger, dehumidifier, air humidifier, steam trap, selective device) are taken according to table 1 of GOST 21.205.

Graphic designations of elements of heating systems (smooth heating pipe, smooth pipe register, ribbed heating pipe, finned pipe register, heating convector, heating radiator, ceiling heating device, air-heating unit, sump) are taken according to table 3 GOST 21.205.

Graphic designations of elements of ventilation and air conditioning systems (air duct, opening (grille) for air intake (exhaust), air distributor, local exhaust (suction, shelter), deflector, umbrella, damper (valve), gate, check valve, fire-retarding valve, hatch for measurements of air parameters and (or) cleaning of air ducts, the passage of ventilation shafts, the ventilation chamber (air conditioner), noise silencer, underground channel) are taken according to table 3 of GOST 21.205.

Graphic designations for the direction of fluid flow, air and drive elements are taken according to table 4 GOST 21.205, tanks, pumps and fans - according to table 5 GOST 21.205, pipeline fittings - according to table 7 GOST 21.205.

Instead of the graphic designation of an axial fan given in Table 5, paragraph 6b of GOST 21.205, the designation according to Table 3* should be adopted.

________________

* Designation adopted according to GOST 2.782.

Table 3

Examples of the image of an axial fan in a diagram made in axonometric projection are shown in Figure 1.

Picture 1

4.9 Conditional graphic images of the main material handling equipment are accepted in accordance with GOST 21.112 and are performed to the scale of the drawing.

Handling equipment, the conditional graphic images of which are not given in the specified standard, are depicted in a simplified way by analogy, taking into account the design features of a particular equipment.

4.10 When depicting a pipeline in a drawing (diagram), alphanumeric designations are indicated on the shelves of leader lines in accordance with Figure 2a and (or) in breaks in pipeline lines in accordance with Figure 2b.

Figure 2

4.11 When specifying the size of the diameter, the sign "" should be written before the dimension number. The designation of the diameter of the pipeline or air duct is applied on the shelf of the leader line in accordance with Figure 3a.

In the event that an alphanumeric designation of the pipeline according to 4.10 is applied on the shelf of the leader line, the diameter of the pipeline is indicated under the shelf of the leader line in accordance with Figure 3b, c.

Figure 3

For pipelines made of steel water and gas pipes (GOST 3262), the nominal diameter and wall thickness are indicated. For pipelines made of steel electric-welded pipes, the outer diameter and wall thickness are indicated. For pipelines from other pipes, similar information is indicated in accordance with the requirements of pipe standards (range, specifications).

In the designation of the section of rectangular air ducts, plotted on the plan of the drawings of systems and located in a horizontal plane, the first digit indicates its width, the second - its height.

4.12 Examples of constructing conventional graphic symbols for system elements are given in Appendix A of GOST 21.205.

Examples of constructing symbols and simplified graphic images of system elements in diagrams performed in axonometric projections are given in Appendix B of GOST 21.205.

4.13 Symbols for devices, automation equipment and communication lines should be taken in accordance with GOST 21.404.

An example of the implementation of a schematic diagram of a ventilation system with an indication of instruments, automation equipment and communication lines is given in Appendix B to GOST 21.205.

The letter designations of the measured quantities and functional features of the devices indicated in the diagram and in the table (Appendix B to GOST 21.205) are adopted in accordance with GOST 21.404.

Examples of letter designations of measured quantities (GOST 21.404) are given in Table 4.

Table 4

Examples of letter designations of functional features of devices (GOST 21.404) are shown in Table 5.

Table 5

Table 6

Image name

Scale

1 Layout of system installations

1:400; 1:800

2 Plans and sections of system drawings

1:50; 1:100; 1:200

3 Diagrams of systems in axonometric projection

1:50; 1:100; 1:200

4 Plans and sections of system installation drawings

1:50; 1:100

5 Fragments of plans and sections of system drawings

1:50; 1:100

6 Nodes of plans and sections of drawings of systems

1:20; 1:50

7 Nodes of plans and sections of drawings of installations of systems

1:20

8 Detailed knots

1:2; 1:5; 1:10

9 Nodes of system diagrams in axonometric projection

1:10; 1:20; 1:50

10 Sketch drawings of general views of non-standard products

1:5; 1:10; 1:20; 1:50; 1:100

4.15 If the image (for example, a plan of drawings of ventilation systems) does not fit on a sheet of the accepted format, then it is divided into several sections, placing them on separate sheets (GOST 21.101).

4.16 When performing the working documentation of heating and ventilation systems, one should also be guided by the requirements of the standards of the Unified Design Documentation System (ESKD) given in Appendix 3 of GOST 21.101, which supplement and do not contradict the SPDS standards and this standard.

If necessary, use separate symbols established by the ESKD standards (classification group 7), if these symbols are not provided for by GOST 21.205 (for example, the designation of an automatic air valve (vent) according to GOST 2.785, the designation of a pump built according to functional features, according to GOST 2.782).

4.17 In the drawings and diagrams, in front of the dimension number that determines the magnitude of the slope, the sign "" is applied, the acute angle of which should be directed towards the slope. The slope value is indicated as a decimal fraction with an accuracy of three decimal places.

The slope designation is applied directly above the contour line (Figure 4a) or on the shelf of the leader line (Figure 4b).

Figure 4

4.18 The list of allowed word abbreviations is given in GOST 2.316 and GOST 21.101.

4.19 On sections (sections) of drawings of systems (installations) and diagrams performed in axonometric projection, marks (GOST 21.101) indicate extension lines (Figure 5a) and (or) contour lines in accordance with Figure 5b.

On the plans of the drawings of systems (installations), marks are indicated in a rectangle in accordance with Figure 5c.

Figure 5

5 General data on working drawings

5.1 General data on working drawings (GOST 21.101) of heating, ventilation and air conditioning systems include:

a) a list of working drawings of the main set;

b) a list of reference and attached documents;

c) a list of the main sets of working drawings;

d) symbols;

e) general instructions;

e) layout plan for the placement of system installations;

g) characteristics of systems;

i) the main indicators according to the working drawings of the OB grade.

5.2 A list of working drawings of the main set (5.1, listing a) is compiled in accordance with Form 1 GOST 21.101.

5.3 The list of reference and attached documents (5.1, listing b) is compiled in accordance with form 2 GOST 21.101.

5.4 A list of the main sets of working drawings (5.1, listing c) is compiled in the form 2 of GOST 21.101 in the presence of several main sets of working drawings of the OB grade and is given on a sheet of general data for each of these sets.

5.5 On the sheet of general data on the working drawings, symbols (5.1, listing d) are given that are not established by state standards, the values ​​of which are not indicated on other sheets of the main set of working drawings of the OB grade.

5.6 In the general instructions (5.1, item e) give:

The basis for the development of working drawings of the OV grade (design assignment, approved feasibility study (project) for construction, approved (approved) justifications for investments in construction for technically simple objects);

A record of the results of the check for patentability and patent purity of processes, equipment, devices, structures, materials and products for the first time used or developed in the project, as well as the numbers of copyright certificates and applications for which decisions were made to issue copyright certificates for inventions used in the working documentation;

A record that the working drawings are developed in accordance with applicable norms, rules and standards;

Information about who owns this intellectual property (if necessary);

Design parameters of outdoor and indoor air;

Data on the heat carrier, coolant (name, consumption, parameters);

Requirements for the manufacture, installation, testing, anti-corrosion protection, thermal and fire insulation, fire-retardant coating of air ducts and pipelines, as well as the composition of insulating structures;

Special requirements for installations (explosion safety, acid resistance, etc.);

List of types of work for which it is necessary to draw up certificates of examination of hidden works.

In general instructions, one should not repeat the technical requirements placed on other sheets of the main set of working drawings of the OV grade, and describe the technical solutions adopted in the working drawings.

5.7 On the layout plan of system installations (5.1, listing e), the following is applied:

Outline of the building (structure);

The coordination axes of the building (structure) and the overall dimensions between the extreme coordination axes;

System installations;

Coolant input;

Thermal point.

The installations of the systems on the plan diagram are depicted by dots with a diameter of 1-2 mm indicating the designation of the installation on the shelf of the leader line and under the shelf - the number of the sheet on which the drawing of the installation is shown.

The name of the plan-scheme for the placement of installations of systems is indicated in abbreviated form as "Plan-scheme".

An example of the implementation of the layout plan for the placement of system installations is given in Appendix B.

5.8 The characteristics of systems (5.1, listing g) are performed in the form of a table in form 1.

System characteristics

Form 1

Continuation of form 1

Continuation of form 1

ending form 1

In the absence of certain types of equipment in the systems, the corresponding columns are excluded from the table.

If the table is divided into parts, then at the beginning of each subsequent part, the column "System designation" is placed.

In typical projects, the characteristics of air heaters and, if necessary, other equipment are indicated for the calculated outside air temperatures adopted by the project.

5.9 The main indicators according to the working drawings of the OB grade (5.1, listing i) are performed in the form of a table in form 2. If necessary, additional columns are included in the table (for example, specific heat consumption).

The main indicators according to the working drawings of the OV grade

Form 2

6 System drawings

6.1 Plans and sections of system drawings

6.1.1 Images - plans and sections, fragments of plans and sections and nodes (remote elements) in the drawings of systems are performed on a scale of 4.14.

6.1.2 Plans of drawings of heating systems (heat supply of installations) may be combined with plans of drawings of ventilation and air conditioning systems. Sections of drawings of heating systems, as a rule, should be combined with sections of drawings of ventilation and air conditioning systems.

6.1.3 Deflectors, roof fans and other elements of systems located on the roof of a building are usually applied with a thickened dash-dot line (superimposed projection) on the plan of drawings of systems of a one-story building or the top floor of a multi-story building. At the same time, complex ventilation installations (for example, air conditioners, supply and (or) exhaust units) located on the roof of the building should be carried out on a separate roof plan. An example of the image of the deflector (BE1 system) located on the roof of the building, on the plan of the drawings of the systems of a one-story building, is shown in Figure 6.

Plan

Figure 6

6.1.4 With a complex multi-tiered arrangement of air ducts and other elements of ventilation and air conditioning systems on the same floor, for clarity of their relationships, plans are made at different levels within the floor.

6.1.5 Pipelines made with conventional graphic symbols (in one line) in accordance with GOST 21.206 and located one above the other in the same plane (Figure 7a), on the plans of the system drawings, are conditionally depicted by parallel lines in accordance with Figure 7b.

Figure 7

6.1.6 Elements of heating and heat supply systems of installations, except for equipment, on plans and sections of drawings of systems indicate by conventional graphic symbols, elements of ventilation and air conditioning systems, as well as equipment of heating and heat supply systems of installations (for example, heating units, pumps) - in the form of simplified graphic images.

6.1.7 On fragments of plans, sections and nodes (remote elements), pipelines, fittings and other devices are depicted in a simplified or conditional graphic designation, depending on the scale of the drawing and the diameter of the pipeline. Pipelines with diameters of 2 mm or more in the drawing are depicted in a simplified way with two lines. When the pipeline is made in a simplified way with two lines, fittings and other devices are also depicted in a simplified way, taking into account their overall dimensions (Figure 8).

Incision

Figure 8

On fragments of plans, sections and nodes (remote elements), the intersection of pipelines without connection, as well as pipelines located one above the other in the same plane and made with conventional graphic symbols (in one line), are depicted in accordance with Figure 9.

Plan

Figure 9

6.1.8 On the plans and sections of the drawings of the systems, apply and indicate:

Coordination axes of the building (structure) and the distance between them (for residential buildings - the distance between the axes of the sections);

Building structures, technological equipment with local suction, as well as border (neighboring) other utilities and equipment that affect the laying of pipelines (air ducts) systems;

Marks of clean floors of floors and main sites;

Dimensional binding of installations of systems, air ducts, main pipelines, process equipment, fixed supports and compensators to the coordination axes or structural elements of the building (structure);

Designations of systems (settings of systems);

Diameters (sections) of air ducts and pipelines;

The number of radiator sections, the number and length of finned pipes, the number of pipes in the register and the length of the register of smooth pipes or the designation of the register, as well as the designation (type) for other heating appliances;

Designations of risers, compensators, horizontal branches of heating systems.

In addition, the plans indicate the names of the premises (types of premises - for residential buildings) and the categories of premises for explosion and fire hazard (in a rectangle measuring 5x8 mm), and on the sections - marks of the levels of the axes of pipelines and round air ducts, the bottom of rectangular air ducts, supporting structures of installations of systems, the top of exhaust air ducts of exhaust systems.

It is allowed to give the names of premises and categories of premises according to explosion and fire hazard in the explication of premises in accordance with Form 2 GOST 21.501.

Examples of the implementation of plans and sections of drawings of systems are given in Appendix B.

6.1.9 In standard designs (standard design solutions) of buildings and structures for two or more design outdoor air temperatures and (or) for two or more floors, the floor number, design outdoor temperature, data on heaters indicated on the plans are given in the table (Figure 10).

Figure 10

If there are several tables in the drawing, it is allowed to give the name of the column only on one of them (Figure 11).

Figure 11

In standard projects (standard design solutions) of buildings and structures for two or more design outdoor temperatures, the diameters of pipelines, if necessary, are indicated in the table.

If there are several tables in the drawing, it is allowed to give the name of the columns only on one of them, and also to exclude individual columns of repeating indicators (Figure 12).

Figure 12

6.1.10 On the sheet of plans for the drawings of the systems, a table of local suctions from process equipment is placed, made in form 3. It is allowed to give a table of local suctions on separate sheets.

Local suction from process equipment

Form 3

Finishing form 3

6.1.11 On plans, sections and their fragments, equipment, installations, air ducts, pipelines and other elements of systems are depicted as a thick main line.

Building structures and technological equipment, as well as border (neighboring) other engineering communications that affect the laying of pipelines (air ducts) of systems (6.1.8), are depicted in plans, sections and their fragments in a simplified way with a thin line.

6.1.12 In the names of the plans of the drawings of the systems indicate the level of the finished floor of the floor or the number of the floor.

Example - Plan for elev. 0.000; Elevation plan +3,600; 4th floor plan.

In the names of the sections of the drawings of the systems, the designation of the corresponding secant plane is indicated.

Example - Section 1-1.

When performing two or more plans at different levels within the floor, the names of the plans indicate the designation of the plane of the horizontal section of the systems.

Example - Plan 3-3.

When executing a part of the plan, the name indicates the axes that limit this part of the plan.

Example - Plan for elev. 0.000 between axes 1-8 and A-D.

6.2 System diagrams

6.2.1 Schemes of systems and nodes (remote elements) of schemes are performed in an axonometric frontal isometric projection on a scale of 4.14. For small buildings, system diagrams take a scale of 1:50.

6.2.2 On the diagrams, the elements of the systems, as a rule, are indicated by conventional graphic symbols. If necessary, the individual elements of the system in the diagram, performed in axonometric projection, are depicted in a simplified way in the form of contour outlines (GOST 21.205, Appendix B).

6.2.3 With a large length and (or) complex arrangement of air ducts and pipelines, it is allowed to depict them with a break in the form of a dotted line. The places of breaks in air ducts and pipelines are indicated in lowercase letters (Figure 13).

Figure 13

6.2.4 On the schemes of heating systems (heat supply of installations) indicate:

Pipelines and their diameters;

Graphic designation of isolated sections of the pipeline (if necessary);

Alphanumeric designations of pipelines;

Level marks of pipeline axes;

Pipeline slopes;

Dimensions of horizontal sections of pipelines (if there are gaps);

Fixed supports, compensators and non-standard fasteners indicating the element designation on the shelf and under the shelf - the document designation;

Shut-off and control valves with an indication of the leader line of the diameter (type) of the valve on the shelf and under the shelf - valve designations according to the catalog (document designations);

Risers (horizontal branches) of heating systems and their designations;

Heating devices;

The number of radiator sections, the number and length of finned tubes, the number of tubes in the register and the length of the register of smooth tubes or the designation of the register, as well as the designation (type) for other heating appliances. For simple heating systems, information on heating devices is not given in the diagram (for example, in the diagram of the heating system of a building of a simple form with a single-row (in plan and height) installation of heating devices);

Designations of installations of systems;

Embedded structures (selective devices for the installation of instrumentation) indicating the designation of the structure and the document. Embedded structures on pipelines and other elements of systems are indicated by dots with a diameter of 2 mm;

Control and measuring devices (if necessary) and other elements of systems. In this case, the letter designations of the measured quantities and functional features of devices (4.13) are taken in accordance with GOST 21.404.

Pipelines and other elements of heating systems (heat supply of installations) are depicted in the diagrams with a thick main line.

Examples of the implementation of schemes for heating and heat supply systems are given in Appendix D.

6.2.5 For residential buildings, it is allowed to carry out schemes of heating systems only for the underground part of the building. For the above-ground part of the building, riser diagrams are performed and, if necessary, a wiring diagram for the attic. When performing riser schemes on the sheets of schemes, the rules for the implementation of these schemes should be given.

6.2.6 On the sheet, which shows the schemes of heating systems and heat supply of installations, as a rule, they give:

Schemes of control units for heating and heat supply systems;

Table of sizes of expansion joints, made according to form 4;

Nodes (remote elements) of schemes of heating systems and heat supply of installations.

Dimensions of compensators, mm

Form 4

In the names of control units for heating and heat supply systems, the unit number is indicated.

Example - Control Node 1; Control node 2.

An example of the implementation of diagrams of control units for heating and heat supply systems is given in Appendix D.

On the nodes for controlling heating and heat supply systems of installations, as well as on the nodes (remote elements) of system diagrams for shut-off and control valves, the diameter (type) of the valve is indicated on the shelf of the leader line and under the shelf - the valve designation according to the catalog (document designation). Similar information is given on the nodes for other elements of the system.

If necessary, to the scheme of the control unit for heating and heat supply systems, the specification is carried out in accordance with form 7 of GOST 21.101 or drawings (plans, sections, diagram and specification) of the system control unit.

An example of the implementation of the scheme of the node (remote element) of the system is given in Appendix D.



GOST
Document indexDocument's nameannotationDownload
GOST 31311-2005

Active.

Heating devices. General specifications.The standard applies to heaters intended for operation in water heating systems of buildings and structures for various purposes.
GOST 27179-86

Active.

Appliances heating accumulative electric household. Safety requirements and test methods.This standard applies to electric storage heaters for domestic or similar purposes, including stoves containing additional direct heating elements.
GOST 27734-88

Active.

Appliances heating direct action electric household. Methods of functional tests.The standard applies to direct-acting electrical heating appliances (hereinafter referred to as appliances) for domestic and similar premises intended for the needs of the national economy and export.
GOST R 53583-2009

Active.

Heating devices. Test methods.The standard applies to heaters intended for operation in the water heating system of buildings for various purposes, and establishes test methods for determining the main operational characteristic - the nominal heat flux, as well as the dependence of the heat flux on the coolant flow rate and the flow patterns of the coolant in the device.
GOST 28669-90

Active.

Electric room heating appliances of accumulative type. Methods for measuring functional characteristics.The standard applies to heating room electrical appliances of the accumulation type, intended for space heating.
This standard does not apply to heating appliances that are part of the building structure, built into heating devices and central heating devices, floor heating installations.
GOST 20219-74

Active.

Apparatus heating gas household with a water circuit.Specifications. State standard of the USSR. Apparatus heating gas household with a water circuit. Specifications. Water contoured heating
household appliances. specifications. GOST 20219-74*.

Active.

Industrial gas burners Classification.Industrial gas burners. Classification. General technical requirements, marking and storage. Committee for Standardization and Metrology of the USSR. Moscow. The state standard of the union cf. gas burners. classification. General technical requirements, marking and storage. GOST 21204-83 (st sev 1051-87)
GOST 21204-83 (st sev 1051-87)

Active.

Safety valves for steam and hot water boilers.Industrial gas burners. Classification. General technical requirements, marking and storage. Committee for Standardization and Metrology of the USSR. Moscow. The state standard of the union cf. gas burners. classification. General technical requirements, marking and storage. GOST 21204-83 (st sev 1051-87)
GOST 21204-97

Active.

Industrial gas burners. General technical requirements.GOST 21204-97: Industrial gas burners. General technical requirements.
Interstate standard. Interstate Council for Standardization, Metrology and Certification.
GOST 25151-82 (st sev 2084-80)

Active.

Water supply. Terms and Definitions.GOST 25151-82 (st sev 2084-80) - Water supply. Terms and Definitions.
GOST 25720-83

Active.

Boilers are water-heating. Terms and Definitions.GOST 25720-83: Hot water boilers. Terms and Definitions.
Standartinform. 2005. Interstate standard.
GOST 20548-87

Active.

Heating water boilers with heat output up to 100 kWGeneral specifications. IPK publishing house of standards.
GOST 10617-83

Active.

Heating boilers with heat output from 0.10 to 3.15 MWGOST 10617-83: Heating boilers with heat output from 0.10 to 3.15 MW. General specifications.
Moscow. Information data.
GOST 20849-94

Active.

Heating convectors. Specifications.GOST 20849-94. Interstate standard. Heating convectors. Specifications.
Interstate Scientific and Technical Commission for Standardization and Technical Rationing in Construction (ISTC).
GOMT 8870-79 Instead of GOST 8870-74

Active.

Hot water columns for bathtubs. Specifications.GOST 8870-79. State Construction Committee of the USSR
Moscow.
State standard of the USSR Union Hot-water columns for bathtubs.
Specifications.
Geysers. specifications.
GOST 8690-94

Active.

Radiators are heating pig-iron. Specifications.GOST 8690-94. Interstate standard. Radiators are heating pig-iron. Specifications.
Interstate scientific and technical commission for standardization and technical regulation in construction.
Moscow.
GOST 21.602-79

Active.

Project documentation system for construction Heating, ventilation and air conditioning.Project documentation system for construction Heating, ventilation and air conditioning.
Working drawings GOST 21.602-79 (st sev 3216-81).
USSR State Committee for Construction Affairs.
Moscow.
SNiP
SNiP 41-01-2003

Active.

Heating, ventilation and air conditioning.These building codes apply to heat supply, heating, ventilation and air conditioning systems in the premises of buildings and structures.
SNiP II-3-79

Active.

Construction heat engineering.Building codes and regulations, building heat engineering and other SNiP standards.
SNiP 2.04.01-85

Active.

Internal plumbing and sewerage of buildings.
SNiP 3.05.01-85

Active.

Internal sanitary systems.
SNiP 3.05.04-85

Active.

External networks and facilities for water supply and sewerage.
SNiP 41-01-2003

Active.

Heating, ventilation and air conditioning.
joint venture
SP 40-102-2000

Active.

Design and installation of pipelines for water supply and sewerage systems made of polymeric materials.
SP 40-104-2001

Active.

Design and installation of underground water supply pipelines from fiberglass pipes.
GESN
GESN-81-02-17-2001

Active.

Water supply and sewerage internal devices.
GESN-2001-16

Active.

Internal pipelines.
GESN-2001-22

Active.

Plumbing - external networks.

The constant use of technical and regulatory documentation of GOST and SNiP is an integral part of the work of engineers, designers, estimators and installers. After all, the compliance of the project with approved state standards and building codes is the key to successful and high-quality work performed and, as a result, the presence of satisfied customers.

For a company specializing in the installation of heating systems, GOST and SNiP regarding heating should become handbooks. No project can be handed over without compliance with building standards. These documents reflect all the requirements for heating systems, provide methods for calculating heat supply and consumable materials, and quality standards for equipment.

The main purpose of these documents is to protect citizens when using construction sites in terms of fire, sanitary and environmental safety, as well as compliance with the requirements for reliability and energy saving for heat supply systems.

Ignoring GOST, SNiP, SP, GESN and VSN standards, building rules and regulations when performing work can lead to unexpected disastrous results. A heating system calculated and installed without taking into account regulatory documents can lead to insufficient thermal conductivity of the system, failure of heating equipment, smoke in rooms or high heating costs due to inefficiency of its operation. Accurate execution of the regulations of the document, which determines the procedure and methods for performing work, will help to avoid failures and breakdowns, as well as further unpleasant proceedings with the customer.

Regulatory documents such as GOST and SNiP, collected in one place, will greatly facilitate the work of the company when performing work on calculations and installing heating systems.

GOST 21.602-2003

INTERSTATE STANDARD

PROJECT DOCUMENTATION SYSTEM
FOR CONSTRUCTION

RULES OF PERFORMANCE

INTERSTATE SCIENTIFIC AND TECHNICAL COMMISSION
FOR STANDARDIZATION AND TECHNICAL REGULATION
IN CONSTRUCTION (MNTKS)

Moscow

Foreword

1 DEVELOPED by the Federal State Unitary Enterprise "Design, Design and Research Institute "SantekhNIIproject"" (FSUE SantekhNIIproekt) and the Federal State Unitary Enterprise "Center for the Methodology of Rationing and Standardization in Construction" (FSUE CNS)

INTRODUCED by Gosstroy of Russia

2 ADOPTED by the Interstate Scientific and Technical Commission for Standardization and Technical Regulation in Construction on October 18, 2002

State name

Name of the public administration body for construction

The Republic of Azerbaijan

Gosstroy of the Republic of Azerbaijan

Republic of Armenia

Ministry of Urban Development of the Republic of Armenia

The Republic of Kazakhstan

Kazstroycommittee

Republic of Kyrgyzstan

State Commission for Architecture and Construction under the Government of the Kyrgyz Republic

The Republic of Moldova

Ministry of Ecology, Construction and Territorial Development of the Republic of Moldova

Russian Federation

Gosstroy of Russia

The Republic of Tajikistan

Komarchstroy of the Republic of Tajikistan

The Republic of Uzbekistan

Goskomarchitektstroy of the Republic of Uzbekistan Ukraine Goskomarchitektstroy of Ukraine

4 INTRODUCED from June 1, 2003 as the state standard of the Russian Federation by the Decree of the Gosstroy of Russia dated May 20, 2003 No. 39

GOST 21.602-2003

INTERSTATE STANDARD

System of design documents for construction

RULES OF PERFORMANCE
HEATING WORKING DOCUMENTATION,
VENTILATION AND AIR CONDITIONING

System of design documents for construction.
Rules for execution of working documentation of heating, ventilation
and air conditioning

4 General provisions

4.1 Working documentation for heating, ventilation and air conditioning is carried out in accordance with the requirements of this standard, GOST 21.101 and other related standards of the Design Documentation System for Construction (SPDS).

4.2 The composition of the working documentation of heating, ventilation and air conditioning systems (hereinafter referred to as systems) includes:

Working drawings intended for the production of construction and installation works (the main set of working drawings of the OB grade);

Sketch drawings of general views of non-standard products, structures, devices, mounting blocks (hereinafter - sketch drawings of general views of non-standard products);

Specification of equipment, products and materials;

Questionnaires and dimensional drawings*;

Local estimate*.

* Perform if necessary.

General data on working drawings;

Drawings (plans, sections and diagrams) of systems;

Drawings (plans and sections) of system installations.

The composition of the main set of working drawings of the OB grade is also allowed to include working drawings of heating points with a coolant input diameter of up to 150 mm.

With mechanical prompting:

supply systems, system installations

exhaust systems, system installations

air curtains

heating units

With a natural urge:

supply systems

exhaust systems

table 2

Riser heating system

Main riser of the heating system

Compensator

horizontal branch

4.7 Pipelines and their elements in the drawings are indicated by conventional graphic symbols and (or) simplified images in accordance with GOST 21.206. When performing pipelines, in a simplified way, as a rule, the general designations provided for by GOST 21.206 are used (table 1, paragraphs 6a and 7a).

Graphic designations of individual elements of pipelines (an isolated section of a pipeline, a pipeline in a pipe (case), a pipeline in an stuffing box, a hydraulic seal, a compensator, a shock-absorbing insert, a place of resistance in the pipeline (throttle washer), a support (suspension) of the pipeline) are taken according to table 6 GOST 21.205.

Alphanumeric designations of pipelines are taken according to table 8 of GOST 21.205.

4.8 Graphic symbols for elements of general use (filter, heater, cooler, heat exchanger, air dryer, air humidifier, steam trap, selective device) are taken according to table 1 GOST 21.205.

Graphic designations of elements of heating systems (smooth heating pipe, smooth pipe register, ribbed heating pipe, finned pipe register, heating convector, heating radiator, ceiling heating device, air-heating unit, mud tank) are taken according to table 3 GOST 21.205.

Graphic symbols for elements of ventilation and air conditioning systems (air duct, opening (grille) for air intake (exhaust), air distributor, local exhaust (suction, shelter), deflector, umbrella, damper (valve), gate, check valve, fire-retarding valve, hatch for measurements of air parameters and (or) cleaning of air ducts, the passage of ventilation shafts, the ventilation chamber (air conditioner), noise silencer, underground channel) are taken according to table 3 of GOST 21.205.

Graphic designations for the direction of fluid flow, air and drive elements are taken according to table 4 GOST 21.205, tanks, pumps and fans - according to table 5 GOST 21.205, pipeline fittings - according to table 7 GOST 21.205.

Instead of the graphic designation of the axial fan, given in the table, paragraph 66 of GOST 21.205, the designation according to the table * should be taken.

* The designation is accepted according to GOST 2.782.

Table 3

Examples of the image of an axial fan in a diagram made in axonometric projection are shown in the figure.

Picture 1

4.9 Conditional graphic images of the main material handling equipment are accepted in accordance with GOST 21.112 and are performed to the scale of the drawing.

Handling equipment, the conditional graphic images of which are not given in the specified standard, are depicted in a simplified way by analogy, taking into account the design features of a particular equipment.

Figure 2

4.11 When specifying the size of the diameter, the sign "Æ" should be written before the dimension number. The designation of the diameter of the pipeline or duct is applied on the shelf of the leader line in accordance with the figure A.

In the case when an alphanumeric designation of the pipeline is applied on the shelf of the leader line, the diameter of the pipeline is indicated under the shelf of the leader line in accordance with Figure b, c.

Figure 3

For pipelines made of steel water and gas pipes (GOST 3262), the nominal diameter and wall thickness are indicated. For pipelines made of steel electric-welded pipes, the outer diameter and wall thickness are indicated. For pipelines from other pipes, similar information is indicated in accordance with the requirements of pipe standards (range, specifications).

In the designation of the section of rectangular air ducts, plotted on the plan of the drawings of systems and located in a horizontal plane, the first digit indicates its width, the second - its height.

4.12 Examples of constructing conventional graphic symbols for system elements are given in Appendix A GOST 21.205.

Examples of constructing symbols and simplified graphic images of system elements in diagrams performed in axonometric projections are given in Appendix B of GOST 21.205.

An example of a schematic diagram of a ventilation system with an indication of instruments, automation equipment and communication lines is given in Appendix B GOST 21.205.

The letter designations of the measured quantities and functional features of the devices indicated in the diagram and in the table (Appendix B GOST 21.205) are adopted according to GOST 21.404.

Examples of letter designations of measured quantities (GOST 21.404) are given in the table.

Examples of letter designations of functional features of devices (GOST 21.404) are given in the table.

Table 4

Table 5

Table 6

1 Layout of system installations

2 Plans and sections of system drawings

1:50; 1:100; 1:200

3 Diagrams of systems in axonometric projection

1:50; 1:100; 1:200

4 Plans and sections of system installation drawings

5 Fragments of plans and sections of system drawings

6 Nodes of plans and sections of drawings of systems

7 Nodes of plans and sections of drawings of installations of systems

8 Detailed knots

9 Nodes of system diagrams in axonometric projection

1:10; 1:20; 1:50

10 Sketch drawings of general views of non-standard products

1:5; 1:10; 1:20; 1:50; 1:100

4.15 If the image (for example, a plan of drawings of ventilation systems) does not fit on a sheet of the accepted format, then it is divided into several sections, placing them on separate sheets (GOST 21.101).

4.16 When performing the working documentation of heating and ventilation systems, one should also be guided by the requirements of the standards of the Unified Design Documentation System (ESKD) given in Appendix 3 of GOST 21.101, which supplement and do not contradict the standards of SPDS and this standard.

If necessary, use separate symbols established by the ESKD standards (classification group 7), if these symbols are not provided for by GOST 21.205 (for example, the designation of an automatic air valve (vent) according to GOST 2.785, the designation of a pump built according to functional features, according to GOST 2.782).

4.17 In the drawings and diagrams, in front of the dimension number that determines the magnitude of the slope, the “Р” sign is applied, the acute angle of which should be directed towards the slope. The slope value is indicated as a decimal fraction with an accuracy of three decimal places.

The designation of the slope is applied directly above the contour line (Figure a) or on the shelf of the leader line (Figure b).

Figure 4

4.18 The list of allowed word abbreviations is given in GOST 2.316 and GOST 21.101.

4.19 On sections (sections) of drawings of systems (installations) and diagrams performed in axonometric projection, marks (GOST 21.101) indicate extension lines (Figure a) and (or) contour lines in accordance with Figure b.

On the plans of drawings of systems (installations), marks are indicated in a rectangle in accordance with figure c.

5.3 List of reference and attached documents (clause , listing b) are in form 2 GOST 21.101.

5.4 List of main sets of working drawings (clause , listing V) are compiled in the form 2 of GOST 21.101 in the presence of several main sets of working drawings of the OB grade and are given on the sheet of general data for each of these sets.

5.5 On the sheet of general data on working drawings, symbols are given (p., listing G), not established by state standards, the values ​​\u200b\u200bof which are not indicated on other sheets of the main set of working drawings of the OV grade.

5.8 Characteristics of systems (clause , enumeration and) is performed in the form of a table in the form of . In the absence of certain types of equipment in the systems, the corresponding columns are excluded from the table.

If the table is divided into parts, then at the beginning of each subsequent part, the column "System designation" is placed.

In typical projects, the characteristics of air heaters and, if necessary, other equipment are indicated for the calculated outside air temperatures adopted by the project.

5.9 The main indicators according to the working drawings of the OB grade (p., listing And) is performed in the form of a table in the form of . If necessary, additional columns are included in the table (for example, specific heat consumption).



6.1.2 Plans of drawings of heating systems (heat supply of installations) may be combined with plans of drawings of ventilation and air conditioning systems. Sections of drawings of heating systems, as a rule, should be combined with sections of drawings of ventilation and air conditioning systems.

6.1.3 Deflectors, roof fans and other elements of systems located on the roof of a building are usually applied with a thickened dash-dotted line (superimposed projection) on the plan of drawings of systems of a one-story building or the top floor of a multi-story building. At the same time, complex ventilation installations (for example, air conditioners, supply and (or) exhaust units) located on the roof of the building should be carried out on a separate roof plan. An example of the image of a deflector (BE1 system) located on the roof of a building, on the plan of drawings of the systems of a one-story building, is shown in the figure.

6.1.4 With a complex multi-tiered arrangement of air ducts and other elements of ventilation and air conditioning systems on the same floor, for clarity of their relationships, plans are made at different levels within the floor.

6.1.5 Pipelines made with conventional graphic symbols (in one line) in accordance with GOST 21.206 and located one above the other in the same plane (Figure a), on the plans of the drawings of the systems, they are conditionally depicted by parallel lines in accordance with figure b .

6.1.6 Elements of heating and heat supply systems of installations, except for equipment, on plans and sections of drawings of systems indicate by conventional graphic symbols, elements of ventilation and air conditioning systems, as well as equipment of heating and heat supply systems of installations (for example, heating units, pumps) - in the form of simplified graphic images.

Figure 6

Incision

Figure 8

On fragments of plans, sections and nodes (remote elements), the intersection of pipelines without connection, as well as pipelines located one above the other in the same plane and made with conventional graphic symbols (in one line), are depicted in accordance with the figure.

Coordination axes of the building (structure) and the distance between them (for residential buildings - the distance between the axes of the sections);

Building structures, technological equipment with local suction, as well as border (neighboring) other utilities and equipment that affect the laying of pipelines (air ducts) systems;

Marks of clean floors of floors and main sites;

Dimensional binding of installations of systems, air ducts, main pipelines, process equipment, fixed supports and compensators to the coordination axes or structural elements of the building (structure);

Designations of systems (settings of systems);

The number of radiator sections, the number and length of finned pipes, the number of pipes in the register and the length of the register of smooth pipes or the designation of the register, as well as the designation (type) for other heating appliances;

Designations of risers, compensators, horizontal branches of heating systems.

In addition, the plans indicate the names of the premises (types of premises - for residential buildings) and the categories of premises for explosion and fire hazard (in a rectangle measuring 5 ´ 8 mm), and on the sections - marks of the levels of the axes of pipelines and round air ducts, the bottom of rectangular air ducts , supporting structures of installations of systems, the top of exhaust air ducts of exhaust systems.

It is allowed to give the names of the premises and the category of premises in terms of explosion and fire hazard in the explication of the premises in accordance with form 2 GOST 21.501.

Examples of the implementation of plans and sections of drawings of systems are given in the appendix.

6.1.9 In standard designs (standard design solutions) of buildings and structures for two or more design outdoor air temperatures and (or) for two or more floors, the floor number, design outdoor temperature, data on heaters indicated on the plans are given in table (figure).

If there are several tables in the drawing, it is allowed to give the name of the column only on one of them (figure).

In standard projects (standard design solutions) of buildings and structures for two or more design outdoor temperatures, the diameters of pipelines, if necessary, are indicated in the table.

Figure 10

Figure 11

If there are several tables in the drawing, it is allowed to give the name of the column only on one of them, and also to exclude individual columns of repeating indicators (figure).

Figure 12

6.1.10 On the sheet of plans for the drawings of the systems, a table of local suctions from process equipment is placed, made in the form. It is allowed to give a table of local suctions on separate sheets.



6.1.11 On plans, sections and their fragments, equipment, installations, air ducts, pipelines and other elements of systems are depicted as a thick main line.

Building structures and technological equipment, as well as border (neighboring) other engineering communications that affect the laying of pipelines (air ducts) of systems (p.), On plans, sections and their fragments, are depicted in a simplified thin line.

6.1.12 In the names of the plans of the drawings of the systems indicate the level of the finished floor of the floor or the number of the floor.

Example - Plan for elev. 0.000; Elevation plan +3,600; 4th floor plan.

In the names of the sections of the drawings of the systems, the designation of the corresponding secant plane is indicated.

Example - Section 1 - 1.

When performing two or more plans at different levels within the floor, the names of the plans indicate the designation of the plane of the horizontal section of the systems.

Example - Plan 3 - 3.

When executing a part of the plan, the name indicates the axes that limit this part of the plan.

Example - Plan for elev. 0.000 between axes 1 - 8 and A - D.

6.2 System diagrams

6.2.1 Schemes of systems and nodes (remote elements) of schemes are performed in an axonometric frontal isometric projection on a scale of . For small buildings, system diagrams take a scale of 1:50.

6.2.2 On the diagrams, the elements of the systems, as a rule, are indicated by conventional graphic symbols. If necessary, the individual elements of the system in the diagram, performed in an axonometric projection, are depicted in a simplified way in the form of contour outlines (GOST 21.205, appendix).

6.2.3 With a large length and (or) complex arrangement of air ducts and pipelines, it is allowed to depict them with a break in the form of a dotted line. The places of breaks in air ducts and pipelines are indicated in lowercase letters (figure).

Figure 13

6.2.4 On the schemes of heating systems (heat supply of installations) indicate:

Pipelines and their diameters;

Graphic designation of isolated sections of the pipeline (if necessary);

Alphanumeric designations of pipelines;

Level marks of pipeline axes;

Pipeline slopes;

Dimensions of horizontal sections of pipelines (if there are gaps);

Fixed supports, compensators and non-standard fasteners indicating the element designation on the shelf and under the shelf - the document designation;

Shut-off and control valves with an indication of the leader line of the diameter (type) of the valve on the shelf and under the shelf - valve designations according to the catalog (document designations);

Risers (horizontal branches) of heating systems and their designations;

Heating devices;

The number of radiator sections, the number and length of finned tubes, the number of tubes in the register and the length of the register of smooth tubes or the designation of the register, as well as the designation (type) for other heating appliances. For simple heating systems, information on heating devices is not given in the diagram (for example, in the diagram of the heating system of a building of a simple form with a single-row (in plan and height) installation of heating devices);

Designations of installations of systems;

Embedded structures (selective devices for the installation of instrumentation) indicating the designation of the structure and the document. Embedded structures on pipelines and other elements of systems are indicated by dots with a diameter of 2 mm;

Control and measuring devices (if necessary) and other elements of systems. In this case, the letter designations of the measured quantities and functional features of the devices (p.) are taken according to GOST 21.404.

Pipelines and other elements of heating systems (heat supply of installations) are depicted in the diagrams with a thick main line.

Examples of the implementation of schemes for heating systems and heat supply installations are given in the appendix.

6.2.5 For residential buildings, it is allowed to carry out schemes of heating systems only for the underground part of the building. For the above-ground part of the building, riser diagrams are performed and, if necessary, a wiring diagram for the attic. When performing riser schemes on the sheets of schemes, the rules for the implementation of these schemes should be given.

6.2.6 On the sheet, which shows the schemes of heating systems and heat supply of installations, as a rule, they give:

Schemes of control units for heating and heat supply systems;

Table of sizes of expansion joints, made according to the form;

Nodes (remote elements) of schemes of heating systems and heat supply of installations.

Dimensions of compensators, mm

In the names of control units for heating and heat supply systems, the unit number is indicated.

Example - Control Node 1; Control node 2.

Examples of the implementation of diagrams of control units for heating and heat supply systems are given in the appendix.

On the nodes for controlling heating and heat supply systems of installations, as well as on the nodes (remote elements) of system diagrams for shut-off and control valves, the diameter (type) of the valve is indicated on the shelf of the leader line and under the shelf - the valve designation according to the catalog (document designation). Similar information is given on the nodes for other elements of the system.

If necessary, to the scheme of the control unit for heating and heat supply systems, the specification is carried out in accordance with form 7 of GOST 21.101 or drawings (plans, sections, diagram and specification) of the system control unit.

An example of the implementation of the scheme of the node (remote element) of the system is given in the appendix.

6.2.7 On the diagrams of ventilation and air conditioning systems indicate:

Air ducts, their diameters (sections) and the amount of passing air in m3 / h (figure);

Graphic designation of isolated sections of the duct (if necessary);

Graphic designation of sections of the duct with a fire-retardant coating;

Level marks of the axis of round and bottom of rectangular air ducts;

Equipment for ventilation installations;

Contours of technological equipment with local suctions (in difficult cases);

Hatches for measuring air parameters and cleaning air ducts with an indication on the shelf of the leader line of the brand of the hatch (p.) and under the shelf - the designation of the document (figure);

Local suctions, their designations and designations of documents. For built-in local suctions supplied complete with process equipment, the designation of the local suction and the designation of the document are not indicated;

Control devices, air distributors, non-standard fasteners (supports) and other elements of ventilation and air conditioning systems, indicating the designation of the system element on the shelf of the leader line and under the shelf - the designation of the document. At the same time, for non-standard products, on the shelf of the leader line, indicate the name and alphanumeric designation of the product (p.) and under the shelf - the designation of the sketch drawing.

Examples of implementation of schemes of ventilation systems are given in the appendix.

Figure 14

Figure 15

6.2.8 In the name of the heating system diagram for two or more systems in the building, the system number is indicated.

In the name of the diagram of the heat supply system of the installations, the designations of the installations are indicated.

In the main inscription, the names of the schemes of heating systems and heat supply of installations are indicated in full.

EXAMPLE Heating system diagram 1; Scheme of the heat supply system for installations P1 - P3.

Above the schemes, the names of the schemes of heating and heat supply systems are indicated in abbreviated form.

EXAMPLE Heating system 1; Heat supply system for installations P1 - P3.

6.2.9 In the names of schemes of ventilation and air conditioning systems, designations of systems are indicated.

In the main inscription, the names of the schemes of ventilation and air conditioning systems are indicated in full.

Example - Schemes of systems P5, B8.

Above the schemes, the names of schemes of ventilation and air conditioning systems are indicated in abbreviated form.

7.3 On the plans and sections of the drawings of the installations, the elements of the installations are depicted in a simplified way. If it is necessary to show the methods of fastening the components of the installation or their connection to each other, the corresponding elements are depicted in detail, as a rule, on the nodes (remote elements) of the plans and sections of the drawings of the installations.

7.4 The rules for depicting pipelines, fittings and other devices on plans, sections and assemblies (remote elements) of installation drawings are accepted according to.

7.5 On the plans and sections of the drawings of installations, apply and indicate:

Coordination axes of the building (structure) and the distance between them;

Marks of clean floors of floors (sites);

Dimensional references of installations to the coordination axes or to structural elements of the building (structure);

The main dimensions and level marks of the installation elements;

Alphanumeric designations of pipelines;

Diameters (sections) of air ducts and pipelines;

Positional designations of equipment, fittings, embedded structures and other devices.

On the plans and sections of the drawings of installations, in addition to the elements of the installations, building structures are indicated.

7.6 On the plans, sections and assemblies of the drawings of installations, equipment, installation structures, pipelines for piping the air cooler and air heater, fittings and other devices are depicted with a thick main line, building structures - with a thin line.

Air ducts located above the equipment (structures) of the installation are usually depicted on the plans as a thickened dash-dotted line (superimposed projection).

Examples of the implementation of plans and sections of drawings of installations are given in the appendix.

7.7 If necessary, as part of the main set of working drawings of the OB grade (p.), draw drawings (plans, sections, assemblies (remote elements) and, as a rule, a schematic diagram) of a heating point in accordance with section. In this case, the schematic diagram is carried out without observing the scale, the actual spatial arrangement of equipment and pipelines is taken into account approximately.

Equipment, pipelines, fittings and other devices in the diagram are indicated by conventional graphic symbols. If necessary, the equipment in the diagram is depicted with simplified external outlines. Embedded structures (selective devices for the installation of instrumentation) in the diagram are indicated by dots with a diameter of 2 mm.

Designed pipelines, fittings and other devices in the diagram are depicted as a solid thick main line. Equipment, as well as pipelines, fittings and other devices supplied complete with equipment or existing, are shown as a solid thin line.

7.8 The diagram is applied and indicated:

Equipment, pipelines, fittings and other devices;

Control and measuring devices (if necessary). In this case, the letter designations of the measured quantities and functional features of the devices (p.) are taken according to GOST 21.404;

Alphanumeric designations of pipelines, as a rule, in breaks in pipeline lines;

Pipeline diameters;

Positional designations of equipment, fittings, embedded structures and other devices;

The direction of the flow of the transported medium.

7.9 On the sheet where the schematic diagram is shown, if necessary, nodes (remote elements) of the diagram and text explanations are given.

7.10 The elements of the installations are assigned reference designations, consisting of the designation of the installation along and the serial number of the element within the installation.

Example - "Settings of systems P1, V1".

8 Sketch drawings of general views of non-standard products

8.1 Sketch drawings of general views of non-standard products (hereinafter referred to as sketch drawings) are performed in accordance with GOST 21.114

8.2 Sketch drawings are developed for non-standard products that are easy to manufacture (structures, devices, mounting blocks (except for heating and ventilation equipment of individual manufacture), designs for fastening pipelines, air ducts, etc.) in the absence of their mass production, standard documentation, standards or other documents for these products.

8.3 Sketch (group sketch) drawing defines the initial design of a non-standard product, contains a simplified image, basic parameters and technical requirements for the product in the amount of initial data (tasks) necessary for the development of design documentation.

The amount of initial data necessary for the development of design documentation for a non-standard product is established by the developer of the draft drawing in accordance with the requirements of GOST 21.114.

Example - Register of smooth pipes GT1, Register of smooth pipes GT2.

8.5 The names of the components of a non-standard product in the sketch drawing are indicated on the shelves of leader lines. The approximate mass of the product is given in the technical requirements for the sketch drawing.

8.6 Sketch drawings are performed on a scale of . It is allowed to make sketch drawings without exact scale, if this does not distort the clarity of the image and does not make it difficult to read the drawing.

An example of a sketch drawing of a general view of a non-standard product is given in Appendix B GOST 21.114.

9 Specification of equipment, products and materials

9.1 The specification of equipment, products and materials (hereinafter referred to as the Specification) is performed in accordance with GOST 21.110, taking into account the requirements of this standard.

9.2 If there is a part or building attached to the production building (structure) in which auxiliary premises are located, the Specification is performed in parts:

Production part;

Auxiliary part.

If a residential building has an annex or an annex that houses public services, then the specification is also compiled in parts:

residential part;

Auxiliary part.

The name of each part is written as a heading in column 2 and underlined.

9.3 The specification or parts thereof are compiled in sections:

Heating;

Heat supply of system installations;

Ventilation or ventilation and air conditioning (if any).

The name of each section is written as a heading in column 2 and underlined.

9.4 Elements of systems (equipment, products) and materials in the Specifications sections are recorded in groups in the following sequence:

in the sections "Heating" and "Heat supply of system installations":

Heating equipment;

Pipeline accessories;

Other elements of systems;

Embedded structures (selective devices for the installation of instrumentation);

pipelines;

Materials.

Pipelines in the Specifications sections are recorded for each diameter. Pipeline elements (bends, transitions, tees, crosses, flanges, bolts, nuts, washers, gaskets) are not included in the Specification;

in the section "Ventilation" ("Ventilation and air conditioning"):

Ventilation equipment;

Other elements of systems;

Embedded structures;

air ducts;

Thermal insulation structures;

Materials.

Air ducts in the Specifications section are recorded for each diameter (section).

Elements of systems (equipment, products) and materials within the specified groups are placed in ascending order of their main parameters (for example, type, brand, diameter, section).

In column 2 "Name and technical characteristics" of the Specification, before the name of equipment, products and materials, indicate their serial number of entry in the Specification within the section. In this case, column 1 "Position" is not filled.

An example of drawing up a specification for equipment, products and materials is given in the appendix.

9.5 The following units of measurement are accepted in the Specification:

Equipment (installations), fittings, air distributors, dampers, local exhausts (shelters), supports (fastenings) of pipelines and air ducts, embedded structures (selective devices for installing instrumentation) and other elements of systems - pcs.;

Radiators - sections/kW (pcs/kW);

Convectors, ribbed pipes, smooth pipe registers - pcs/kW;

Pipelines and air ducts - m;

Insulating materials - m3;

Coating and protection materials - m2;

Other materials - kg.

10 Questionnaires and dimensional drawings

10.1 Questionnaires and dimensional drawings are performed in accordance with the data of equipment manufacturers and are completed in the form of a separate issue with the name "Questionnaires".

The issue "Questionnaires" is assigned an independent designation, consisting of the designation of the main set of working drawings of the OV brand and through the cipher point "OL". The designation is indicated on the title page of the issue of questionnaires.

Example - 2345-11-OV.OL.

10.2 After the title page of the issue of questionnaires, the content is placed. The content is performed in accordance with form 2 GOST 21.101. The content is assigned a designation consisting of the designation of the issue of questionnaires and the code "C".

Example - 2345-11-OV.OLS.

Sheets of contents draw up the main inscription. On the first sheet of content, the main inscription is performed in accordance with form 5 GOST 21.101 and on subsequent sheets - in form 6 GOST 21.101. In column 5 of the main inscription indicate "Content".

In the column "Designation" - the designation or serial number of the questionnaire (outline drawing);

In the column "Name" - the name of the questionnaire (outline drawing) in full accordance with the name indicated on the questionnaire (outline drawing);

In the column "Note" - information about the changes made to the questionnaires (dimensional drawings).

Heating system project includes a text part and a set of drawings in accordance with the requirements of regulatory documentation.

The scope of project documentation, i.e. heating project includes:

    at the stage of development of the wiring diagram:
  • cover and title page;
  • table of initial data for designing a heating system;
  • basic technical solutions for heating systems (summary);
  • calculations are made that are not included in the design documentation:
    • performance of heat engineering calculation (determination of heat losses of the building);
    • calculation of the power of heating devices;
    • hydraulic calculation of heating mains and their elements;
    • calculation of the main heating equipment (boilers, boilers, etc.);
  • main set of drawings:
    • placement of terminal equipment (heaters and consoles);
    • placement of heating mains and their elements;
  • specification of heating equipment without details;
    to receive a complete package of project documentation, i.e. creating a heating project, additionally developed:
  • added to the main set of drawings:
    • areas of operation and maintenance of the main heating equipment;
    • detailing the nodes of the main heating equipment (piping of boilers, boilers and thermal units);
    • block diagram of the main heating equipment;
    • detailing the nodes of the terminal heating equipment system (drawing manifold cabinets, detailing the boiler room and chimneys, connecting heaters);
    • overall dimensions (diameters) and service areas of heating lines;
    • notes for installation of the heating system;
    • schemes of the heating system;
  • added to the explanatory note:
    • table of heat demand of the building by systems;
    • characteristics of the heating system (dimensions, energy consumption, etc.);
    • design of heating system automation;
  • assignment to related systems (integration table) - issued upon request, if other companies are engaged in related engineering systems;
  • specification of heating equipment with details;
  • licenses and certificates for design and installation works;
  • coordination of design decisions with architects and designers.

The scope of the heating project allows you to fully implement the designed system. Some of the documents included in the heating project being developed by our company are presented in the standard combined heating project for a house.

Detailed composition of project documentation

Detailed composition of project documentation for the section of the project on heating, heat networks and thermal mechanical solutions of the boiler house at various stages of work attached to a contract for design and survey work.

Here we present this application in its entirety.

The name of the documentation section Stage of work
Draft design / Draft scheme Wiring diagram Project
1. Cover* + + +
2. Title page* + + +
3. Approval sheet** - + +
4. Content* - - +
5. Scope of the project* - - +
6. Terms of Reference** + + +
7. Specifications (when received from the customer) - + +
8. Explanatory note, including **: + + +
8.1. Details of the document on the basis of which the decision was made to develop project documentation - + +
8.2. Initial data and conditions for the preparation of project documentation + + +
8.3. Information about the functional purpose of the object + + +
8.4. Information about the object's need for fuel, gas, water, electric energy, thermal energy, the amount of air supplied and removed, and cold. Information is given in text or tabular form - + +
8.5. Technical and economic indicators of the designed facilities - - +
8.6. General information about systems - + +
8.7. General characteristics of the designed systems and their networks - + +
8.8. Information on the availability of developed and agreed special technical conditions - if necessary, the development of such conditions - + +
8.9. Assurance of the design organization that the heating project has been developed in accordance with the design assignment, technical regulations, including those establishing requirements for ensuring the safe operation of buildings, structures, structures and the safe use of the territories adjacent to them, and in compliance with the technical specifications - - +
8.12. For the heating and heat networks section, the HVAC project includes the following data:
8.12.1. Information about the climatic and meteorological conditions of the construction area, the design parameters of the outside air - - +
8.12.2. Information about sources of heat supply, parameters of heat carriers of heating systems - + +
8.12.3. Description and justification of laying methods and design solutions, including decisions regarding the diameters and thermal insulation of pipes of the heating main from the point of connection to public networks to the facility - - +
8.12.4. List of measures to protect pipelines from the aggressive effects of soils and groundwater - - +
8.12.5. Substantiation of adopted systems and fundamental decisions on space heating - + +
8.12.6. Information on heat loads for heating, hot water supply, production and other needs - - +
8.12.7. Justification of the optimal placement of heating equipment - - +
8.12.8. Description of automation of heating and heat supply systems - - +
8.12.9. Information about the requirements (according to SP 7.13130.2009) for the following premises: boiler room, heating point, reserve fuel storage rooms - + +
9. The main set of working drawings, including:
9.1. Display of the adopted technical and other solutions and is carried out in the form of drawings, diagrams, plans and other documents in graphic form - + +
9.4. The heating and heat networks section includes the following data:
9.4.1. Plan of heating networks with plotted heating mains and their elements - + +
9.4.2. Overall dimensions of heating mains and heating network routes - - +
9.4.4. Placement of the main heating equipment + + +
9.4.5. Overall dimensions of the main equipment for heating and heating networks - + +
9.4.6. Areas of operation and maintenance of the main equipment - - +
9.4.7. Detailing of the nodes of the main equipment of the heating system - - +
9.4.8. Block diagram of the heating system - + +
9.4.9. Notes required for installation - - +
9.4.10. Axonometric diagram of the heating system - - +
9.4.11. Location of terminal heating equipment - + +
9.4.12. Overall dimensions of the terminal equipment of heating systems and heat networks - + +
9.4.13. Zones of operation and maintenance of terminal heating equipment - - +
9.4.14. Detailing of terminal equipment units - - +
10. Assignment to adjacent systems** - + +
11. Specification without equipment details** - + -
11.3. The heating and heat networks section includes the following data:
11.3.5. Heat generating plant (boiler, heating network, etc.) and its components, as a single set - + -
11.3.6. Zone closers (climatic devices) for air temperature and their components, as a single set - + -
11.3.7. Tanks-water heaters and their components, as a single set - + -
11.3.8. Expansion tanks and their components as a single set - + -
11.3.9. The main main manifold with mixing units and their components, as a single set - + -
11.3.10. Chimney and its components, as a single set - + -
11.3.11. Automation of the main heating equipment and its components, as a single set - + -
11.3.12. Equipment that provides storage and supply of reserve fuel and its components, as a single set - + -
11.3.13. Burner equipment and its components, as a single set - + -
11.3.15. Lines are indicated with material, size, type and manufacturer as a set - + -
11.3.16. Consumables for each type of heating equipment and mains are indicated as a set - + -
12. Specification for heating equipment and materials, made in accordance with GOST - - +
13. Permits for design and survey work - + +

Notes:

    one asterisk indicates * - design documentation in accordance with GOST
    two asterisks denote ** - in the amount and form determined by the Contractor
    The designation "-" corresponds - the document is not in the package of documents developed at this design stage
    The designation "+" corresponds - the document is present

Example projects with description

Some of the documents included in the heating project developed by our company are presented in